OUR PLACE

City Springs Development

Development of City Springs will create a new center point for the City of Sandy Springs—its “heartbeat”. The new civic and cultural center will contain City Offices, a Performing Arts Center, a studio theater, meeting space, retail and residential spaces, a city green and underground community parking.

Our City

Incorporated in 2005, the City of Sandy Springs is home to almost 100,000 residents and is a corporate home to a robust business community. World renowned for its pioneering Public-Private-Partnership model of local governance, the City is at the center of the Atlanta-Metro area’s business district. You can learn more about the City on it’s website, sandyspringsga.gov.

Development Team

The City Springs project is being led by the City of Sandy Springs. Master development for the project is being conducted by a partnership between Carter and Selig Enterprises. Rosser International is the architect for the civic facilities, and jB+a, Inc. is the Landscape Architect. Holder Construction Company is the project’s Construction Manager.

The City Springs District

Allen Road borders the City Springs District to the District’s south, and Johnson Ferry Road provides the northern boundary line. Learn more about the City Springs District.

Construction Progress

Construction of the 14-acre triangle central area, which will house the civic facility and performing arts center, began summer 2015 with completion slated for summer 2018. See how construction is progressing. You can also view the project’s webcam.

Master Plan

Following a yearlong, public-involved planning process in late 2012, the Sandy Springs City Council adopted a master plan to develop the City’s downtown area.

Latest News

Construction Activity Update for the Week of November 16, 2017

Construction Activities This Week Site/Park Continued Installation of Sidewalks at Johnson Ferry & Sandy Springs Circle & Mt. Vernon Hwy....

Construction Activity Update for the Week of November 9, 2017

Construction Activities This Week Site/Park Continued Installation of Sidewalks at Johnson Ferry & Sandy Springs Circle. Continued Construction of the...

Construction Activities for the Week of November 2, 2017

Construction Activities This Week Site/Park Continued Installation of Sidewalks at Johnson Ferry & Sandy Springs Circle. Continued Construction of the...

City Springs Time Lapse Video, October 2017

This is a 31 day time lapse of work being completed at City Springs in Sandy Springs, Georgia in October...

Construction Activity Updates for the Week of October 26, 2017

Construction Activities This Week Site/Park Continued Installation of Sidewalks at Johnson Ferry & Sandy Springs Circle. Continued Construction of the...

Construction Activity Update for the Week of October 19, 2017

Construction Activity This Week Site/Park Continued Installation of Sidewalks at Johnson Ferry & Sandy Springs Circle. Continued Construction of the...

Construction Activity Update for the Week of October 12, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Waterproofing. Continued Installation of Sidewalks at Johnson Ferry & Sandy Springs...

Construction Activity Update for the Week of October 5, 2017

Construction Activity This Week Site/Park Continued Market Square Fountain Waterproofing. Continued Installation of Sidewalks at Johnson Ferry & Sandy Springs...

City Springs Time Lapse Video, September 2017

This is a 30 day time lapse of work being completed at City Springs in Sandy Springs, Georgia in September...

Construction Activity Update for the Week of September 28, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade...

Construction Activity Update for the Week of September 21, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade...

Construction Activity Update for the Week of September 14, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade...

Construction Activity Update for the Week of September 7, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade...

City Springs Time Lapse Video, August 2017

This is a 31 day time lapse of work being completed at City Springs in Sandy Springs, Georgia in August...

Construction Activity Update for the Week of August 31, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade...

Construction Activities for the Week of August 17, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade...

Construction Activity Updates for the Week of August 10, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP Wall Installation. Continued Installation of Pavers at Shade...

Construction Activities for the Week of August 3, 2017

Construction Activities This Week Site/Park Completed Waterproofing Installation of Waterwall & Plaza and Interactive Fountain. Continued Market Square Fountain Structure...

City Springs Time Lapse Video, July 2017

This is a 31 day time lapse of work being completed at City Springs in Sandy Springs, Georgia in July...

Construction Activity Update for the Week of July 27, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP wall installation. Continued Construction of the Restroom Building....

Construction Activity Update for the Week of July 20, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP wall installation. Continued Construction of the Restroom Building....

Construction Activity Update for the Week of July 13, 2017

Construction Activities This Week Site/Park Continued Market Square Fountain Structure and CIP wall installation. Continued Construction of the Restroom Building....

City Springs Video Update – Summer 2017

Summer 2017 construction update on the City Springs development in Sandy Springs, Georgia, USA. Music by bensound.com.

Construction Activity Update for the Week of July 06, 2017

Construction Activities This Week Site/Park Commenced Market Square Fountain Structure and CIP wall installation. Continued Construction of the Restroom Building....

Construction Activity Update for the Week of June 29, 2017

Construction Activity This Week Site/Park Completed Sidewalk Installation at Fidelity Bank. Continued Construction of the Restroom Building. Continued Installation of...

City Springs Topic of Retail Industry Meeting

City Springs was the topic for the June meeting of ICSC and P3Retail. The panel discussion included Sandy Springs Mayor...

Construction Activity Update for the Week of June 22, 2017

Construction Activities This Week Site/Park Completed Installation of Pumps in the Interactive/ Plaza Fountain Vault. Completed Waterproofing Installation at the...

Construction Activity Update for the Week of June 15, 2017

Construction Activities This Week Site/Park Continued Construction of the Restroom Building. Continued Installation of Pumps in the Interactive/ Plaza Fountain...

Construction Activity Updates for the Week of June 8, 2017

Construction Activities This Week Site/Park Continued Construction of the Restroom Building. Continued Installation of Plaza & Interactive Fountain. Continued Forming...

City Springs Time Lapse Video, May 2017

This is a 31 day time lapse of work being completed at City Springs in Sandy Springs, Georgia in May...

Construction Activity Updates for the Week of June 1, 2017

Construction Activities This Week Site/Park Continued Construction of the Restroom Building. Continued Installation of Plaza & Interactive Fountain. Continued Waterproofing...

Construction Activity Updates for the Week of May 25, 2017

Construction Activities  This Week Site/Park Continued Construction of the Restroom Building. Continued Installation of Plaza & Interactive Fountain. Continued Waterproofing...

Construction Activities for the Week of May 18, 2017

Construction Activities This Week Site/Park Continued Construction of the Restroom Building. Continued Installation of Plaza & Interactive Fountain. Continued Waterproofing...

Construction Activity Updates for the week of May 11, 2017

Construction Activities This Week Site/Park Completed Structure Installation of the Waterwall Fountain. Continued Construction of the Restroom Building. Continued Installation...

Construction Activities for the Week of May 4, 2017

Construction Activities This Week Site/Park Continued Construction of the Restroom Building. Continued Installation of Veneer at Plaza & Interactive Fountain....

City Springs Time Lapse Video, April 2017

This is a 30 day time lapse of work being completed at City Springs in Sandy Springs, Georgia in April...

Construction Activity Update for the Week of April 27, 2017

Construction Activities This Week Site/Park Completed Slab Pour of the Restroom Building. Continued Installation of Veneer at Plaza & Interactive...

Construction Activities for the week of April 20, 2017

Construction Activities This Week Site/Park Completed Forming of Planters, Site Walls & Stair at the City Green. Continued Forming of...

Construction Activities for the week of April 13, 2017

Construction Activities This Week Site/Park Completed Demobilization of Tower Crane. Continued Forming of Planters, Site Walls & Stair at the...

Construction Activities for the week April 6, 2017

Construction Activities This Week Site/Park Continued Forming of Planters, Site Walls & Stair at the City Green. Continued Forming of...

Construction Activities for the week of March 30, 2017

Construction Activities  This Week Site/Park Continued Forming of Planters, Site Walls & Stair at the City Green. Continued Forming of...

Construction Activities for the week of March 23, 2017

Construction Activities This Week Site/Park Completed Final Tie-in of E-10 Storm Structure. Continued Forming of Planters, Site Walls & Stair...

Construction Activities for the week of March 16, 2017

Construction Activities This Week Site/Park Continued Forming of Planters, Site Walls & Stair at the City Green. Continued MEP Installation...

Construction Activities for the week of March 9, 2017

Construction Activities This Week Site/Structure Completed Final Slab Pour of the PAC Fountain. Continued Forming of Planters, Site Walls &...

Construction Activities for the week of March 2, 2017

Construction Activities This Week Site/Structure Continued PAC Fountain Slab Walls and Slabs. Continued Installation of Storm Drainage above CIP Parking...

Construction Activities for the week of February 24, 2017

Construction Activity This Week Site/Structure Continued PAC Fountain Slab Prep. Continued Installation of Storm Drainage above CIP Parking Deck. Continued...

Construction Activities for the week of February 17, 2017

Construction Activities This Week Site/Structure Completed Lower Basin Slab Install for the PAC Fountain. Continued Installation of Storm Drainage above...

Construction Activities for the week of February 9, 2017

Construction Activities This Week Site/Structure Completed Pouring of Slip Ramp Walls. Continued Piping Installation for PAC Fountain. Continued Installation of...

Construction Activities for the week of February 2, 2017

Construction Activities This Week Site/Structure Continued Elevator Installation at Precast Deck. Continued Piping Installation for PAC Fountain. Continued Installation of...

Construction Updates for the week of January 26, 2017

Construction Activities This Week Site/Structure Continued Elevator Installation at Precast Deck. Continued Piping Installation for PAC Fountain. Continued Installation of...

Construction Activities for the week of January 19, 2017

Construction Activities This Week Site/Structure Continued Elevator Installation at Precast Deck. Continued Excavation for PAC Fountain. Continued Forming of Slip...

Construction Activities for the week of January 12, 2017

Construction Activities This Week Site/Structure Continued Elevator Installation at Precast Deck. Continued Installation of Storm Drainage above CIP Parking Deck....

Construction Activities for the week of January 5, 2017

Construction Activities This Week Site/Structure Continued Elevator Installation at Precast Deck. Continued Installation of Storm Drainage above CIP Parking Deck....

Construction Activities for the week of December 29, 2016

Construction Activity This Week Site/Structure Completed Slip Ramp SOG Installation. Continued Elevator Installation at Precast Deck. Continued Installation of Storm...

Construction Activities for the week of December 15, 2016

Construction Activities This Week Site/Structure Complete Installation of LS/HS Mockup on Bluestone. Continued Grading for SOG at Office Tower. Continued...

Construction Activities for the week of December 8, 2016

Construction Activities This Week Site/Structure Continued Grading for SOG at Office Tower. Continued Elevator Installation at Precast Deck. Commence Slip...

Construction Activities for the week of December 1, 2016

Construction Activities This Week Site/Structure Completed Interior Waterproofing of the Irrigation Cistern. Completed Slip Ramp Excavation and Shoring Wall Installation....

Construction Activities for the week of November 17, 2016

Construction Activities This Week Site/Structure Completed Utility Line Installation to the Performance Art Theatre. Continued Interior Water-Proofing of the Irrigation...

Construction Activities for the week of November 16, 2016

Construction Activities This Week Site/Structure Completed Installation of Grease Traps North of Office Tower. Completed Backfill at Area D Lid....

Construction Activities for the week of November 3, 2016

Construction Activities This Week Site/Structure Performing Arts Center Continued Architectural Precast Installation at the East Elevation. Completed Installation of Ramps...

Construction Activities for the week of October 27, 2016

Construction Activities This Week Site/Structure Continued Backfill of the Storm Trap System (Irrigation Cistern) Continued Installation of Grease Traps North...

Construction Activities for the week of October 20, 2016

Construction Activities This Week Site/Structure Continued Backfill of the Storm Trap System (Irrigation Cistern) Continued Installation of Grease Traps North of...

Video Update – October 2016

October 2016 construction update on the City Springs development in Sandy Springs, Georgia, USA. Music by bensound.com.

Construction Activities for the week of October 13, 2016

Construction Activities This Week Site/Structure Completed Installation of the Storm Trap System (Irrigation Cistern) Continued Installation of Hardscape Mockup. Continued Installation...

Construction Activity for the week of October 6, 2016

Construction Activities This Week Site/Structure Completed Installation of Grease traps at the Fidelity Bank Site. Continued Installation of Hardscape Mockup. Commenced...

Construction Activities for the week of September 29, 2016

Construction Activities This Week Site/Structure Completed Subgrade Prep for the Construction of the Irrigation Cistern. Completed Installation of Grease traps at...

Construction Activities for the week of September 22, 2016

Construction Activities This Week Site/Structure Completed Excavation and Installation of Shoring Walls for the Construction of the Irrigation Cistern. Continued Installation...

Construction Activities for the week of September

Construction Activities This Week Site/Structure Continued Installation of Grease traps at the Fidelity Bank Site. Continued Excavation and Installation of Shoring...

Construction Activities for the week of September 08, 2016

Construction Activities This Week Site/Structure Completed Underslab Drainage Installation at Area E. Continued Installation of Grease traps at the Fidelity Bank...

Construction Activities for the week of September 1, 2016

Construction Activities This Week Site/Structure Completed Dirt Ramp removal in to CIP Deck. Completed Installation of the G2 Structure along...

Construction Activities for the week of August 25, 2016

This Week’s Construction Activities Site/Structure Completed Installation on Sanitary Sewer along Mt. Vernon Hwy. Continued Dirt Ramp removal in to CIP...

Construction Activities for the week of August 18, 2016

Construction Activities This Week Site/Structure Completed Underground Storm, Water and Fire line Installation South of Area G. Completed Underground Duct Bank...

Construction Activities for the week of August 11, 2016

This Week’s Construction Activities Site/Structure Completed Under Slab Drainage at Area D. Continued Installation of Grease traps at the Fidelity Bank...

Construction Activities for the week of August 4, 2016

This Week’s Construction Activities Site/Structure Continued Installation of Grease traps at the Fidelity Bank Site. Continued backfill of the lid at...

Applications Accepted for General Manager Position

Comcast Spectacor, the private contractor overseeing management of the Performing Arts Center, is seeking applications for the position of General...

Construction Activities for the week of July 28, 2016

This Week’s Activities Site/Structure Commenced Installation of Grease traps at the Fidelity Bank Site. Continued backfill of the lid at Area...

Construction Activities for the week of July 21, 2016

This Week’s Activities Site/Structure Completed Water Fountain Piping (Plaza & Interactive) Installation South of Area G. Continued Underground Storm Line installation...

Construction Activities for the week of July 14, 2016

This Week’s Construction Activities Site/Structure Commenced Water Fountain Piping (Plaza & Interactive). Installation South of Area G. Continued Underground Storm...

Construction Activities for the week of July 7, 2016

This Week’s Construction Activities Site/Structure Continued Underground Storm Line installation South of Area G. Continued Underground Duct Bank installation South of Area...

Construction Activities for the week of June 30, 2016

This Week’s Construction Activities Site/Structure Commenced Underground Storm Line installation South of Area G. Commenced Underground Duct Bank installation South of Area...

Construction Activities for the week of June 23, 2016

This Week’s Construction Activities Site/Structure Continued perimeter drain installation of the lid. Performing Arts Center Continued Re-Steel Installation at Gallery...

Construction Activities for the week of June 16, 2016

This Week’s Construction Activities Site/Structure Continued Underground Storm Line at Market Square Installation. Performing Arts Center Commenced Re-Steel Installation at Gallery...

Video Update – June 2016

June 2016 construction update on the City Springs development in Sandy Springs, Georgia, USA. Music by bensound.com.

Construction Activities for the week of June 9, 2016

This week’s construction activities Site/Structure Continued Underground Storm Line at Market Square Installation. Performing Arts Center Poured Raker Beams at Balcony...

Construction Activities for the week of June 2, 2016

This Week’s Construction Activities Site/Structure Continued Underground Storm Line at Market Square Installation. Performing Arts Center Poured Raker Beams at Balcony Level...

Construction Activities for the week of May 26, 2016

This Week’s Construction Activities Site/Structure Continue Underground Storm Line at Market Square Installation. Performing Arts Center Continued Raker Beam Re-Steel Installation....

Construction Activities for the week of May 19, 2016

This Week’s Construction Activities Site/Structure Continued Underground Storm Line at Market Square Installation. Performing Arts Center Commenced Raker Beam Form Work Installation....

Construction Activities for the week of May 12, 2016

This Week’s Construction Activities Site/Structure Began Underground Storm Line at Market Square Installation. Performing Arts Center Commence Raker Beam Form...

Construction Activities for the week of May 05, 2016

This Week’s Construction Activities Site/Structure Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck Performing Arts Center Completed Area C3...

Construction Activities for the week ending April 22, 2016

This Week’s Construction Activities Site/Structure Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck Performing Arts Center Completed Gravel Back...

Construction Activities for the week ending April 15, 2016

Road Closure Alert:  The intersection of Mt Vernon Highway and Sandy Springs Circle takes place on Monday, April 18, 2016....

Construction Activities for the week ending April 7, 2016

This Week’s Construction Activities Site/Structure Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck Performing Arts Center Completed Gravel Back...

Video Update – Mar. 2016

March 2016 construction update on the City Springs development in Sandy Springs, Georgia, USA. Music by bensound.com.

Construction Activities for the week ending March 25, 2016

This Week’s Construction Activities Site/Structure Complete Site Excavation to Grade in at Southwest Private Deck in Support of Shotcrete Wall...

Construction Activities for the week ending March 18, 2016

This Week’s Construction Activities Site/Structure Continue Site Excavation to Grade in at Southwest Private Deck in Support of Shotcrete Wall...

Construction Activities for the week ending March 11, 2016

This Week’s Construction Activities Site/Structure Continue Site Excavation To Grade at Southwest Private Deck in Support of Shotcrete Wall Installation,...

Construction Activities for the Week of March 4, 2016

This Week’s Construction Activities Site/Structure Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck...

Construction Activities for the week of February 26, 2016

Precast material deliveries for the parking deck began arriving this week. Trucks will stage off-site with deliveries made “just in...

Construction Activities for the week of February 19, 2016

This Week’s Construction Activities Site/Structure Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck...

Design Update Presentation

During a public meeting at City Hall today, the City Springs design team presented updated designs for the public components...

Construction Activities for the week of February 12, 2016

This Week’s Construction Activities Site/Structure Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck...

Video Update – Feb. 2016

February 2016 construction update on the City Springs development in Sandy Springs, Georgia, USA. Music by bensound.com.

Construction Activities for the week of February 5, 2016

Construction Activities Impacting Traffic Flow:  A lane closure is underway on the northern-most lane on Johnson Ferry Road, beginning at Ferry Drive...

Construction Activities for the week of January 29, 2016

This Week’s Construction Activities Site/Structure Completed Tower Crane Installation Continued Site Excavation to Drilled Pier Grade in Performing Arts Center,...

Construction Activities for the week of January 15, 2016

This Week’s Construction Activities Site/Structure Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck...

Construction Activities for the Week of January 8, 2016

Construction Activities Impacting Traffic Flow: Beginning February 1, 2016, the northern-most lane on Johnson Ferry Road, beginning at Ferry Drive...

Construction Activities for the Week of December 18, 2015

ACTIVITIES THIS WEEK: Site / Structure Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private...

Construction Activities for the Week of December 11, 2015

THIS WEEK’S ACTIVITIES We began pouring concrete at the site of the performing arts center this week, a noteworthy milestone.  The...

Construction Activities for the Week of December 4, 2015

Activities This Week Site/Structure Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in...

Construction Activities for the week of November 20, 2015

Current Construction Activities Site/Structure Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in...

Construction Update for November 12, 2015

Activities This Week: Site Structure Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck...

Construction Update for November 5, 2015

Activity This Week: Site Structure Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck...

Construction Update for October 29, 2015

This Week’s Activities Site/Structure Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in...

Construction Update for October 22, 2015

This Week’s Activities Site/Structure Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in...

Construction for update for October 15, 2015

Activities This Week Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support...

Construction Update for October 9, 2015

This Week’s Activities Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, Continue Excavation at East Deck, Commence...

Construction Update for Oct 2, 2015

Activities This Week Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, Continue Excavation at East Deck, Commence...

Construction Update for Sept. 25, 2015

Activities This Week Continue Site Excavation To Drilled Pier Grade in Performing Arts Center Continue H-Pile Drilling/Installation for Shoring Wall...

Construction Update for Sept. 18, 2015

ACTIVITIES THIS WEEK Continue Excavation Along Southwest Side of West Deck Commence Temporary Construction Dewatering Well Drilling Commence H-Pile Drilling/Installation...

Construction Update for Sept. 11, 2015

This Week’s Activities Excavation and Bench to Drilled Pier Grade at East Side of Performing Arts Center Mobilize Temporary Construction...

Construction Update for Sept. 4, 2015

Activities This Week Excavated to Drilled Pier Grade at City Office Building Excavated to Drilled Pier Grade at Studio Theatre...

Watch What Happened on the Construction Site – August 2015

While the fence wrapping and vehicles moving rapidly around prevent a good view of what is happening within the city...

Construction Update for August 28, 2015

THIS WEEK’S ACTIVITIES Continue Site Excavation Removal of Contaminated Soil Mobilize Shoring Rig Completed Soil Boring Testing Conference Trailer Mobilization Erosion...

Construction Update August 21, 2015

THIS WEEK’S ACTIVITIES Site Excavation Removal of Existing Building Foundations Erosion Control Monitoring and Maintenance Layout of Additional Soil Test Borings...

Construction Update August 14, 2015

THIS WEEK’S ACTIVITIES Site Excavation Removal of Existing Building Foundations Installation of Project Webcam Erosion Control Monitoring and Maintenance Layout...

The Great Dig

One feature of the new development is the addition of underground parking. To make that happen, a good bit of...

Construction Update August 7, 2015

THIS WEEK’S ACTIVITIES Completion of Site Clearing & Grubbing Continuation of Tree Removal Construction Office Mobilization Georgia Power Commencement of...

Construction Update July 31, 2015

THIS WEEK’S ACTIVITIES Site Clearing & Grubbing Continues Tree Removal Continues Construction Office Mobilization Removal of Existing Building Foundations Complete...

Presentation from Public Information Open House – March 4, 2015

More than 200 people attended the March 4, 2015 meeting that featured a presentation of design concepts. Here’s a link...

Sandy Springs Seeks Community Input on Visual Preference for City Center

Please Note: This meeting has been postponed due to a Winter Weather Warning. It will now be held on Wednesday, March...

Construction Activities for the week of January 22, 2016

This Week’s Construction Activities Site/Structure Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck...

Sandy Springs Selects Holder Construction as Construction Manager at Risk for City Center

The City of Sandy Springs today announced it has selected Holder Construction Company as Construction Manager at Risk (CMAR) to...

Venue Solutions Group Submit Management Options for the Performing Arts Center

The Sandy Springs Mayor and City Council attended a Special Called Retreat today. During the retreat they received a draft...

Preliminary Recommendations on the Design and Governance of Performing Arts Center

Rick Davis, Executive Director of the Hylton Performing Arts Center submitted preliminary recommendations on the design and governance of the...

Photos taken at Performing Arts Center Charrette

During a lively charrette today, the City garnered feedback from performance industry organizations.

Sandy Springs to Host Charrette on Programming Its Performing Arts Center

Workshop targeted to visual, performing and musical arts and business planners  The City of Sandy Springs is seeking input from...

Sandy Springs City Council Approves Site Development Plan for City Center

At the September 2, 2014 council meeting, the Sandy Springs City Council unanimously approved a site development plan for the...

Special Called City Council Meeting on August 27 Gets Large Turnout

More than 180 people attended the August 27, special-called meeting of the Sandy Springs City Council, which included a presentation...

Community Members Help Develop City Center Vision during Open House Meeting

More than 100 community members visited the Public Open House meeting at City Hall yesterday to give their input on...

Performing Arts Center and Meeting Space Update Presented to Mayor and City Council

Members of the Sandy Springs community attended a presentation on the proposed Performing Arts Center and Meeting Space given to the...

Sandy Springs featured in Georgia Municipal Association video on Excellence by Design

During its June 2014 annual meeting, the Georgia Municipal Association presented a video on Excellence by Design – how cities...

City of Sandy Springs Takes Next Step in Selection of City Center Master Planner

SANDY SPRINGS (June 18, 2014)  – The City of Sandy Springs today announced it has selected Carter/Selig Enterprises (Carter/Selig) as...

City Installs Temporary Lawn

The City added a lawn this week to help with erosion control until construction begins on the site of the...

Crews begin Demolition of Former Waffle House Building

As demolition began on the former Waffle House building today, hungry waffle-lovers enjoyed a hearty breakfast at the brand new...

Former Target Demolition Kicks-Off the City Center Development Project

People from the Sandy Springs community braved freezing temperatures today to watch the demolition of the City-owned former Target building....

Plan Elements Reviewed at Community Open House

There were a few familiar faces, and lots of new faces at the public open house meeting held at City...

Transportation Infrastructure the Topic of Conversation at Community Meeting

The Sandy Springs City Center Master Plan community meeting held yesterday evening, focused on transportation infrastructure. The event kicked-off with...

Community Members Help Define Character of Downtown Development through Visual Preference Survey

With a series of broad concepts in place for the Sandy Springs City Center Master Plan, Goody Clancy once again...

Sandy Springs Community Members take First Look at Draft Master Plan Concepts

Members of the Sandy Springs community had the opportunity to discover Goody Clancy’s concepts for the future of the City’s...

Open House Format Workshop Furthers Public Involvement in the Planning Process

Taking place from 8:00 a.m.-6:00 p.m., today’s open house format workshop offered an opportunity for residents and business owners to...

The Planning Process Continues with Public Participation

This morning’s City Center Development workshop had a strong attendance from residents and business owners who were keen to contribute...

June Public Workshop Series Begins

The Goody Clancy team presented their research to Sandy Springs residents and businesses this evening, at an event which kicks-off...

Holy Innocents’ 4th-Graders Share their Ideas with City Council

Students from Sandy Springs Holy Innocents’ School presented their plans for the old Target Property and City Center development to...

Residents and Businesses Attend Community Meetings

Sandy Springs Residents and businesses took the opportunity to meet with Goody Clancy today and express their ideas and opinions...

Stakeholders Meet with Goody Clancy

For the last three days, Goody Clancy has been conducting a series of stakeholder meetings regarding the development of the...

Goody Clancy Presents to Sandy Springs City Council

Members of the Sandy Springs City Council met with representatives of Boston based planning firm, Goody Clancy today during their...