Construction Activity Update for the Week of December 14, 2017

Construction Activities This Week Site/Park Continued Exterior Skin Installation at the Restroom Building. Continued Paver Installation at Mt. Vernon Hwy, Johnson Ferry and PAC. Continued Waterproofing Installation at Arrival Court Fountain. Continued Installation of Trees at the Park. Continued Curb & Gutter Installation at South...

Continue reading...

Construction Activity Update for the Week of December 7, 2017

Construction Activities This Week Site/Park Completed Installation of Sidewalks at Mt. Vernon Hwy. Continued Exterior Skin Installation at the Restroom Building. Continued Paver Installation at Mt. Vernon Hwy, Johnson Ferry and PAC. Continued Waterproofing Installation at Arrival Court Fountain. Continued Installation of Trees at the...

Continue reading...

Take Your Seat

City of Sandy Springs sets the stage creating community nucleus for the arts. Two years ago, the junction of Roswell Road, Johnson Ferry Road, Mt Vernon Highway and Sandy Springs Circle in Sandy Springs, Ga. was a non-descript parking lot, dotted with box retailers cycling...

Continue reading...