Construction Updates for the week of January 26, 2017

Construction Activities This Week

Site/Structure

  • Continued Elevator Installation at Precast Deck.
  • Continued Piping Installation for PAC Fountain.
  • Continued Installation of Storm Drainage above CIP Parking Deck.
  • Continued Forming and Pouring of Slip Ramp Walls.
  •  Commenced Layout of Site Walls & Planters at City Green.

Performing Arts Center

  • Continued Catwalk and Handrail Backwelding for the Flyloft at Area C2.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continued Installation of Brick at North Elevation.
  • Continued Roofing Installation.
  • Continued Installation of Exterior Glass/Glazing at North & East Elevation.

Office Tower & Studio Theatre

  • Continued MEP Overhead Rough-In at Lobby Level.
  • Continued Architectural Precast Installation (Studio Theatre) at South Elevation.
  • Continued CMU Wall Installation at Service Level.
  • Continued Chiller Plant Piping Installation.
  • Continued Roof Level Misc. Steel Install.
  • Continued Top Track Installation at Conference Level.
  • Continued Glass/Glazing Prep Work.
  • Continued High Roof Parapet Framing.

CIP Deck

  • Continued Installation of Waterproofing at Area F Lid Level.
  • Continued Fire Protection Installation.
  • Continued Equipment Room Buildout.
  • Commenced Pouring Arcade Slabs.

Roadways

  • Continued Grading of South Parking.
  • Commenced Installation of Curb & Gutter at Blue-stone/Hilderbrand.
  • Commenced Jack & Bore Operation at Sandy Spring Circle & Johnson Ferry.

Construction Activities Next Week

Site/Structure

  • Continue Elevator Installation at Precast Deck.
  • Continue Installation of Storm Drainage above CIP Parking Deck.
  • Continue Piping for PAC Fountain.
  • Continue Forming & Pouring of Slip Ramp Walls.
  • Continue Site Walls & Planters at City Green.

Performing Arts Center

  • Continue Catwalk and Handrail Backwelding for the Flyloft at Area C2.
  • Continue Landing Prep of North and South Stairs.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continue Installation of Exterior Glass/Glazing at North & East Elevation.
  • Continue Installation of Brick at North Elevation.
  • Continue Roofing Installation.

Office Tower & Studio Theatre

  • Continue MEP Overhead Rough-In at Lobby Level.
  • Continue Architectural Precast Installation (Studio Theatre) at South Elevation.
  • Continue CMU Wall Installation at Service Level.
  • Continue Chiller Plant Piping Installation.
  • Continue Roof Level Misc. Steel Install.
  • Continue Top Track Installation at Conference Level.
  • Continue Glass/Glazing Prep Work.
  • Continue High Roof Parapet Framing.

CIP Deck

  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area F Lid Level.
  • Continue Equipment Room Buildout.
  • Continue Pouring Arcade Slab.

Roadways

  • Continue Grading of South Parking.
  • Continue Installation of Curb & Gutter at Bluestone/Hilderbrand.
  • Commence Paving at Bluestone/Hilderbrand.
  • Commence Jack & Bore Operation at Sandy Spring Circle & Johnson Ferry.