Construction Update for Sept. 18, 2015

ACTIVITIES THIS WEEK

  • Continue Excavation Along Southwest Side of West Deck
  • Commence Temporary Construction Dewatering Well Drilling
  • Commence H-Pile Drilling/Installation for Shoring Wall System at Southwest Corner of Private Deck
  • Excavating Low Level Impacted Soils in Southeast Section of Site
  • Erosion Control Monitoring and Maintenance
  • Deliver Deep Foundation Rebar for Performing Arts Center Foundations

ACTIVITIES NEXT WEEK

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center
  • Continue H-Pile Drilling/Installation for Shoring Wall System at Southwest Private Deck
  • Continue Temporary Construction Dewatering System Installation
  • Deep Foundation Drilling and Installation at Performing Arts Center Elevation 1100’
  • Continue Excavation at East City Parking Deck
  • Continue Georgia Power Trenching at Sandy Springs Circle