This Week’s Activities

  • Excavation and Bench to Drilled Pier Grade at East Side of Performing Arts Center
  • Mobilize Temporary Construction Dewatering Rigs
  • Excavating to Top of Shoring Wall Grade South City Parking Deck
  • Erosion Control Monitoring and Maintenance
  • Georgia Power Crossing Sandy Springs Circle with Underground Utility on to West Side of Site

 

Next Week’s Activities

  • Continue Site Excavation at Drilled Pier Grade in PAC
  • H-Pile Drilling/Installation for Shoring Wall System at Northwest City Parking Deck
  • Commence Temporary Construction Dewatering System Installation
  • Mobilize Deep Foundation Material for Performing Arts Center Foundations
  • Commence Excavation at East City Parking Deck
  • Georgia Power Commencing Underground Utility Activities Along Sandy Springs Circle