Construction Update for October 9, 2015

This Week’s Activities

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, Continue Excavation at East Deck, Commence Excavation at Southwest Private Deck in Support of Shotcrete Wall Installation.
  • Continue H-Pile Drilling/Installation for Shoring Wall System at Southwest Private Deck.
  • Continue Temporary Construction De-watering System Installation.
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1100’.
  • Continue Georgia Power Trenching and Conduit Installation at Sandy Springs Circle.
  • Began Shotcrete and Waterproofing at Southwest Private Deck Shoring Walls

Next Week’s Activities

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue Temporary Construction De-watering System Installation.
  • Continue H-Pile Installation at West Deck and Commence H-Pile Installation at East Deck.
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1100’.
  • Continue Georgia Power Trenching at Sandy Springs Circle.
  • Continue Shotcrete at Southwest Private Deck Shoring Walls.