Construction Update for October 29, 2015

This Week’s Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation at West Deck and East Deck: Grid Line PW-PE.E on P6
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and W1– T2.
  • Commence Shotcrete at Southwest Private Deck Shoring Walls: Grid Line P7-P11 & PA.1-PE.7
  • Commence Testing Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line PA—P11 & PE.7-P7.
  • Continue Shotcrete Prep in West Deck and East Deck: Grid Line PG-PH at P0.1-P1 & T7-08 at PE.E

Other

  • Continue Temporary Construction Dewatering System Installation.
  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Continue Pre-Blasting Line Drilling

Next Week’s Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation at East Deck: Grid Line PE.E-PJJ on P6
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and T3 – T4.
  • Continue Shotcrete at Southwest Private Deck Shoring Walls: Grid Line PA-P11 & PE.7-P7.
  • Commence Testing Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line PA—P11 & PE.7-P7.
  • Commence Shotcrete in West Deck and East Deck: Grid Line PG-PH at P0.1-P1 & T7-08 at PE.E
  • Continue Shotcrete Prep in West Deck and East Deck: Grid Line PA-PS at P1-R6 and PE.E-PJ.J at P1-P6

Other

  • Continue Temporary Construction Dewatering System Installation.
  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Continue Pre-Blasting Line Drilling