This Week’s Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation at West Deck and East Deck: Grid Line PN-OA & PS-PW
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and W1– T2.
  • Continue Shotcrete Prep at Southwest Private Deck Shoring Walls: Grid Line PA-P11 & PE.7-P7.
  • Commence Tie-Back Installation at Southwest Private Deck Shoring Walls: Grid Line PA—P11 & PE.7-P7.
  • Commence Shotcrete Prep in West Deck and East Deck: Grid Line PG-PH at P0.1-P1 & T7-08 at PE.

Other

  • Continue Temporary Construction Dewatering System Installation.
  • Continue Georgia Power Trenching at Sandy Springs Circle.
  • Continue Pre-Blasting Line Drilling

Next Week’s Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation at West Deck and East Deck: Grid Line PW-PJJ
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and W1– T2.
  • Commence Shotcrete at Southwest Private Deck Shoring Walls: Grid Line PA-P11 & PE.7-P7.
  • Testing Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line PA—P11 & PE.7-P7.
  • Continue Shotcrete Prep in West Deck and East Deck: Grid Line PG-PH at P0.1-P1 & T7-08 at PE.E

Other

  • Continue Temporary Construction Dewatering System Installation.
  • Commence Georgia Power Trenching at Mount Vernon HWY NE
  • Continue Pre-Blasting Line Drilling