Construction Update for Oct 2, 2015

Activities This Week

Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, Continue Excavation at East Deck, Commence Excavation at Southwest Private Deck in Support of Shotcrete Wall Installation.
Continue H-Pile Drilling/Installation for Shoring Wall System at Southwest Private Deck.
Continue Temporary Construction De-watering System Installation.
Continue Deep Foundation Installation at Performing Arts Center Elevation 1100’.
Continue Georgia Power Trenching and Conduit Installation at Sandy Springs Circle.
Commence Top of Wall Lagging at Southwest Private Deck Shoring Walls
Activities Next Week

Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
Continue Temporary Construction De-watering System Installation.
Continue H-Pile Installation at West Deck and Commence H-Pile Installation at East Deck.
Continue Deep Foundation Installation at Performing Arts Center Elevation 1100’.
Continue Georgia Power Trenching at Sandy Springs Circle.
Commence Shotcrete at Southwest Private Deck Shoring Walls.