Construction Update for November 5, 2015

Activity This Week: Site Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continued H-Pile Installation at East Deck: Grid Line PE.E-PJJ on P6
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and T3 -T4.
  • Continued Shotcrete at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7.
  • Commenced Testing Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7
  • Commenced Shotcrete in West Deck and East Deck: Grid Line PA-PH at P6-06 and T7-08 at TE
  • Commenced Tie-Backs at West Deck Shoring Walls: Grid Line PG-PH & P1-P0.1.
  • Continued Shotcrete Prep in West Deck and East Deck: Grid Line PA-PH at P6-06 and T7-08 at TE

Other

  • Continued Temporary Construction Dewatering System Installation.
  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Continued Pre-Blasting Line Drilling in West Deck between PL-PP on P1

Next Week’s Activities:  Site Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation at West and East Deck with Kelly Bar: Grid Lines P6-P7 & PH-PM and P4-P6 & PF.F-PJ.J
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and T3 – T4.
  • Continue Shotcrete at Southwest Private Deck, West Deck, and East Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P6-06, and TE-PJ.J & T7-P4.
  • Continue Shotcrete Prep in Southwest Private Deck, West Deck, and East Deck : Grid Line P7—P11 & PA.1-PE.7, PA-PS & P6-06, and TE-PJ.J & T7-P4.
  • Continue Tie-Backs at West Deck Shoring Walls: Grid Line PG-PH & P1-P0.1.
  • Commence Tie-Backs at East Deck Shoring Walls: Grid Line T7-08 at TE.

Other

  • Continue Temporary Construction Dewatering System Installation.
  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Continue Pre-Blasting Line Drilling in West Deck and East Deck: Grid Line PP-PS & P1-06 and PF.F-PJ.J & P4-P6
  • Approximately 106,800 cubic yards of dirt have been removed from the site.