Activities This Week: Site Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continued H-Pile Installation in West Deck with Kelly Bar: Grid Lines P6-P7 & PH-PM and P4-P6 & PF.F-PJ.J
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and T3 – T4.
  • Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PG & P1-P6.
  • Continue Shotcrete Prep in Southwest Private Deck, West Deck, and East Deck : Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6, and T7-08 at TE.
  • Continued Tie-Backs at West Deck Shoring Walls: Grid Line PG-PH & P1-P0.1.
  • Commenced Tie-Backs at East Deck Shoring Walls: Grid Line T7-08 at TE.

Other

  • Continued Temporary Construction Dewatering System Installation.
  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Continued Pre-Blasting Line Drilling in West Deck and East Deck: Grid Line PP-PS & P1-06 and PF.F-PJ.J & P4-P6

Activities Next Week: Site Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation in West Deck with Kelly Bar: Grid Lines P6-P7 & PH-PM
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and T4 – T5.
  • Continue Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PH-PS & P1-P6.
  • Continue Shotcrete Prep in Southwest Private Deck, West Deck, and East Deck : Grid Line P7—P11 & PA.1-PE.7, PH-PS & P1-P6, and T7-08 at TE.
  • Continue Tie-Backs at West Deck and East Deck Shoring Walls: Grid Line PG-PH & P1-P0.1, and T7-08 at TE.

Other

  • Continue Temporary Construction Dewatering System Installation.
  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Continue Pre-Blasting Line Drilling in East Deck: Grid Line PB.B-PF.F & P4-P6