THIS WEEK’S ACTIVITIES

  • Continue Site Excavation
  • Removal of Contaminated Soil
  • Mobilize Shoring Rig
  • Completed Soil Boring Testing
  • Conference Trailer Mobilization
  • Erosion Control Monitoring and Maintenance

NEXT WEEK’S ACTIVITIES

  • Continue Site Excavation
  • H-Pile Material Procurement
  • H-Pile Delivery / Layout (CIP Deck)
  • Install Temporary Dewatering
  • Measures
  • Pre-Split Drilling for Subsurface Rock Removal