Construction Update August 7, 2015

THIS WEEK’S ACTIVITIES

  • Completion of Site Clearing & Grubbing
  • Continuation of Tree Removal
  • Construction Office Mobilization
  • Georgia Power Commencement of Power Line Relocation
  • Continuation of Dirt Excavation
  • Commence Project Layout and Control
  • Design Review of Loading Dock Layout
  • Layout and Additional Testing of Impacted Soils

 

NEXT WEEK’S ACTIVITIES

  • Continue Site Grading and Excavation
  • Continue Establishment of Construction Offices
  • Install Project Webcam
  • Continue Project Layout and Control
  • Continue Removal of Existing Under-ground utilities
  • Foundation Contractor Mobilize Personnel and Equipment to Site
  • Commence Impacted Soils Excavation and Haul-off