Construction Update August 14, 2015

THIS WEEK’S ACTIVITIES

  • Site Excavation
  • Removal of Existing Building Foundations
  • Installation of Project Webcam
  • Erosion Control Monitoring and Maintenance
  • Layout of Additional Soil Test Borings
  • Establish Construction Roads
  • Site Prep for Drilled Piers (PAC)
  • Completed Construction Office Mobilization

NEXT WEEK’S ACTIVITIES

  • Continue Site Excavation
  • Removal of Contaminated Soil
  • Mobilize Soil Test Boring Rig
  • Mobilize Shoring Rig
  • Continue Site Prep for Drilled Piers (PAC)