Construction for update for October 15, 2015

Activities This Week

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation at West Deck and East Deck: PJJ-P4 and PH-PN.
  • Complete Deep Foundation Installation at Performing Arts Center Elevation 1100’: Grid Lines ZA—ZB.
  • Commence Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA.
  • Continue Shotcrete at Southwest Private Deck Shoring Walls: Grid Line PA—P11 & PE.7-P7.
  • Continue Temporary Construction Dewatering System Installation.
  • Continue Georgia Power Trenching at Sandy Springs Circle.
  • Commence Pre-Blasting Line Drilling

Activities Next Week

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation at West Deck and East Deck: Grid Line PN –OA.
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA– TC.5.
  • Continue Shotcrete at Southwest Private Deck Shoring Walls: Grid Line PA—P11 & PE.7-P7.
  • Commence Tie-back Installation at Southwest Private Deck: Grid Line PA—P11 & PE.7-P7.
  • Commence Shotcrete Prep in West Deck: Grid Line PA–P6-PF.
  • Continue Temporary Construction Dewatering System installation.
  • Continue Georgia Power Trenching at Sandy SpringsCircle.
  • Continue Pre-Blasting Line Drilling