Construction Activities This Week
Site/Park
- Continued Construction of the Restroom Building.
- Continued Installation of Plaza & Interactive Fountain.
- Continued Forming of Planters, Site Walls & Stair at the Shade Bosque.
- Continued Sub-slab Installation at City Green.
- Commenced Installation of Sidewalks at Mt.Vernon Hwy.
Performing Arts Center
- Completed CE-01 Elevator Installation.
- Completed Installation of Walk-in Cooler.
- Continued Hanging & Finishing Hard Ceilings.
- Continued Overhead MEP Rough-in at PAC Lobby & Gallery Level.
- Continued Fire Protection Installation at Gallery Level and Lobby Bar.
- Continued Plaster Installation.
- Continued Brick Installation at North Elevation.
- Continued Installation of Glass/Glazing at VIP lounge.
- Commenced Startup of AHU-1 and AHU-6.
- Commenced Installation of Ceramic Tile at Restrooms.
Office Tower & Studio Theatre
- Continued Metal Panel Installation.
- Continued Stair Installation.
- Continued Chiller and Cooling Tower Start-up.
- Continued Tile Installation at Kitchen.
- Continued Installation of Glass/Glazing.
- Continued Roofing Installation at Office Tower.
- Continued Framing of Hard Lid Ceilings at Service, Lobby, Gallery Levels.
- Continued Installation of AE03 & AE08 Service Elevators.
- Completed Brick Installation at North Elevation.
CIP Deck
- Continued East Deck Sprinkler Pipe Installation.
- Continued East Deck Sprinkler Room Buildout.
- Continued Point, Patch, and Rub of Columns and Sheer-walls at East Deck.
- Continued PAC Fountain Room Buildout.
Roadways/Public Utility
- Continued SSC West Storm Drainage work.
- Continued GA Power Jack & Bore at Roswell Rd.
Construction Activities Next Week
Site/Park
- Continue Restroom Building CMU Installation.
- Continue Installation of Plaza & Interactive Fountain.
- Continue Waterproofing of the PAC Fountain.
- Continue Forming of Planters, Site Walls & Stair at the Shade Bosque.
- Continue Sub-slab Installation at City Green.
- Continue Installation of Sidewalks at Mt.Vernon Hwy.
Performing Arts Center
- Continue hanging Hard Ceilings.
- Continue Overhead MEP Rough-in at PAC Lobby & Gallery Level.
- Continue Fire Protection Installation at Gallery Level and Lobby Bar.
- Continue Plaster Installation.
- Continue MEP Overhead Installation at Lobby Level.
- Continue Installation of Glass/Glazing at VIP lounge.
- Continue Startup of AHU-1 and AHU-6.
- Continue Installation of Ceramic Tile at Restrooms.
Office Tower & Studio Theatre
- Continue Metal Panel Installation.
- Continue Stair Installation.
- Continue Chiller and Cooling Tower Start-up.
- Continued Conference Level Parapet Waterproofing.
- Continue Installation of Glass/Glazing.
- Continue Roofing Installation at Office Tower.
- Continue Acoustical Spray Insulation at Studio Theater.
- Continue Framing of Hard Lid Ceilings at Service, Lobby, and Gallery Levels.
- Continue Installation of Tile at Kitchen.
- Continue Installation of AE03 & AE08 Service Elevators.
CIP Deck
- Continue East Deck Sprinkler Pipe Installation.
- Continue East Deck Sprinkler Room Buildout.
- Continue Point, Patch, and Rub of Columns and Sheerwalls at East Deck.
- Continue PAC Fountain Room Buildout.
Roadways/Utilities
- Continue Sandy Springs West Stormwork.