Construction Activity Update for the Week of September 7, 2017

Construction Activities This Week

Site/Park

  • Continued Market Square Fountain Structure and CIP Wall Installation.
  • Continued Installation of Pavers at Shade Bosque and City Green.
  • Continued Construction of the Restroom Building.
  • Continue Flatwork Installation at PAC & Market Square.

Performing Arts Center

  • Continued Hanging & Finishing Hard Ceilings.
  • Continued Plaster Installation.
  • Continued Installation of Glass/Glazing at VIP lounge.
  • Continued Installation of Ceramic Tile at Restrooms.
  • Continued Installation of Restroom Fixtures.
  • Continued Installation of Wood Reflectors.
  • Continued Installation of Rigging Materials above stage.

Office Tower & Studio Theatre

  • Continued Metal Panel Installation.
  • Continued Installation of Pipe Grid.
  • Continued Stair Installation.
  • Continued Installation of Glass/Glazing.
  • Continued Roofing Installation at Office Tower.
  • Continued Framing of Hard Lid Ceilings at all levels.
  • Continued Installation of AE05, AE06 & AE07 Elevators.
  • Continued Exhaust and UDS Install at Kitchen.
  • Continued Prime Coat Paint Installation at all levels.
  • Continued FRP Installation at Kitchen.

CIP Deck

  • Continued East Deck Sprinkler Pipe Installation.
  • Continued GE01 Elevator Installation.
  • Continued Point, Patch, and Rub of Columns and Sheer-walls at East Deck.
  • Continued Area G and PAC Fountain Room Buildout.
  • Continued Area D Pop up Installation.

Roadways/Public Utility

  • Continued Curb and Gutter Installation at Johnson’s Ferry Rd.
  • Continued Interior Roadway Prep at Market Square.

Construction Activities Next Week

Site/Park

  • Continue Market Square Fountain Structure and CIP wall installation.
  • Continued Installation of Pavers at Shade Bosque and City Green.
  • Continue Construction of the Restroom Building.
  • Continue Flatwork Installation at PAC & Market Square.
  • Continue Installation of Veneer at Waterwall Fountain.

Performing Arts Center

  • Continue Hanging Hard Ceilings.
  • Continue Plaster Installation.
  • Continue MEP Overhead Installation at Lobby Level.
  • Continue Installation of Glass/Glazing at VIP lounge.
  • Continue Installation of Ceramic Tile at Restrooms.
  • Continue Installation of Restroom Fixtures.
  • Continue Installation of Mid-Reflectors.
  • Continue Installation of Rigging Materials above stage.

Office Tower & Studio Theatre

  • Continue Metal Panel Installation.
  • Continue Installation of Pipe Grid.
  • Continue Stair Installation.
  • Continue Installation of Glass/Glazing.
  • Continue Roofing Installation at Office Tower.
  • Continue Framing of Hard Lid Ceilings at all levels.
  • Continue Installation of AE05, AE06 & AE07 Elevators.
  • Continue Exhaust and UDS Install at Kitchen.
  • Continue Prime Coat Paint Installation at all levels.
  • Continue FRP Installation at Kitchen.
  • Commence Kitchen Equipment Installation.

CIP Deck

  • Continue East Deck Sprinkler Pipe Installation.
  • Continued Installation of GE-01 Elevator.
  • Continue Point, Patch, and Rub of Columns and Sheerwalls at East Deck.
  • Continue PAC and Area G Fountain Room Buildout.
  • Continue Area D Pop up Installation.

Roadways/Utilities

  • Continue curb & gutter installation at JF.
  • Continue Interior Roadway Prep at Market Square.