Construction Activity Update for the Week of September 28, 2017

Construction Activities This Week

Site/Park

  • Continued Market Square Fountain Structure and CIP Wall Installation.
  • Continued Installation of Pavers at Shade Bosque and City Green.
  • Continued Construction of the Restroom Building.
  • Continue Flatwork Installation at PAC & Market Square.
  • Began Flatwork at J.F North Parcel.

Performing Arts Center

  • Continued Hanging & Finishing Hard Ceilings.
  • Continued Plaster Installation.
  • Continued Installation of Glass/Glazing at VIP lounge.
  • Continued Installation of Rear GWB Reflectors.
  • Continued Prime and Paint Drywall and Plaster.

Office Tower & Studio Theatre

  • Continued Metal Panel Installation.
  • Continued Framing of Hard Lid Ceilings at all levels.
  • Continued Installation of AE04 – AE07 Elevators.
  • Continued Prime Coat Paint Installation at all levels.
  • Continued Installation of Millwork and Casework.
  • Continued Installation of Quartz Countertops at Bathrooms.
  • Continued Installation of Navy Island Micro-perf Panels at Studio Theater.

CIP Deck

  • Continued Painting of Hollow Metal Doors and Frames.
  • Continued East Deck Sprinkler Pipe Installation.
  • Continued GE01 and GE02 Elevator Installation.
  • Continued Point, Patch, and Rub of Columns and Sheer-walls at East Deck.
  • Continued Area G and PAC Fountain Room Buildout.
  • Continued Area D Pop up Installation.

Roadways/Public Utility

  • Continued Curb and Gutter Installation at South Parking Lot.
  • Continued Installation of Islands at Johnson’s Ferry Rd. and Sandy Spring Circle.
  • Continued Paving and Interior Roadway Prep.

Construction Activities Next Week

Site/Park

  • Continue Market Square Fountain Structure and CIP wall installation.
  • Continue Installation of Pavers at Shade Bosque and City Green.
  • Continue Construction of the Restroom Building.
  • Continue Flatwork Installation at PAC & Market Square.
  • Continue Installation of Veneer at Waterwall Fountain.

Performing Arts Center

  • Continue Hanging Hard Ceilings.
  • Continue Plaster Installation.
  • Continue MEP Overhead Installation at Lobby Level.
  • Continue Installation of Glass/Glazing at VIP lounge.
  • Continue Installation of Ceramic Tile at Restrooms.
  • Continue Installation of Restroom Fixtures and Accessories.
  • Continue Installation of Millwork “Trees” and Wood Caps.
  • Continue Installation of Rigging Materials above stage.

Office Tower & Studio Theatre

  • Continue Metal Panel and Glazing Installation.
  • Continue Roofing Installation at Office Tower.
  • Continue Framing of Hard Lid Ceilings at all levels.
  • Continue Installation of AE04 – AE07 Elevators.
  • Continue Kitchen Equipment Installation.
  • Continue Prime Coat Paint Installation at all levels.
  • Continue Installation of Millwork and Casework.
  • Continue Quartz Countertops Installation at Bathrooms.
  • Continue Tile Installation at Office Tower Lobby.
  • Continue Installation od Navy Island Micro-perf Panels.

CIP Deck

  • Continue East Deck Sprinkler Pipe Installation.
  • Continue Installation of GE01 and GE02 Elevators.
  • Continue Point, Patch, and Rub of Columns and Sheerwalls at East Deck.
  • Continue PAC and Area G Fountain Room Buildout.
  • Continue Area D Pop up Installation.

Roadways/Utilities

  • Continue curb & gutter installation at JF and South Parking.
  • Continue Installation of Islands at Johnson Ferry and Sandy Spring Circle.