Construction Activity Update for the Week of October 19, 2017

Construction Activity This Week

Site/Park

  • Continued Installation of Sidewalks at Johnson Ferry & Sandy Springs Circle.
  • Continued Construction of the Restroom Building.
  • Continued Flatwork Installation at Market Square.
  • Continued Paver Installation at Sandy Springs Circle and Johnson Ferry.
  • Continued Installation of Arrival Court Fountain.
  • Completed Market Square Fountain Waterproofing.

Performing Arts Center

  • Continued Hanging Hard Ceilings.
  • Continued Plaster Installation.
  • Continued MEP Overhead Installation at Lobby Level.
  • Continued Installation of Glass/Glazing at VIP lounge.
  • Continued Installation of Ceramic Tile at Restrooms.
  • Continued Installation of Restroom Fixtures and Accessories.
  • Continued Installation of Millwork “Trees” and Wood Caps.
  • Continued Installation of Rigging Materials above stage.

Office Tower & Studio Theatre

  • Continued Metal Panel and Glazing Installation.
  • Continued Roofing Installation at Office Tower.
  • Continued Framing of Hard Lid Ceilings at all levels.
  • Continued Installation of AE04 – AE07 Elevators.
  • Continued Kitchen Equipment Installation.
  • Continued Prime Coat Paint Installation at all levels.
  • Continued Installation of Millwork and Casework.
  • Continued Quartz Countertops Installation at Bathrooms.
  • Continued Tile Installation at Office Tower Lobby.
  • Continued Installation of Navy Island Micro-perf Panels.

CIP Deck

  • Continued East Deck Sprinkler Pipe Installation.
  • Continued Installation of GE01 and GE02 Elevators.
  • Continued PAC and Area G Fountain Room Buildout.
  • Continued Area D Pop up Installation.

Roadways/Public Utility

  • Commenced Exterior Roads Final Paving.

Construction Activity Next Week

Site/Park

  • Continue Installation of Sidewalks at Johnson Ferry & Sandy Springs Circle.
  • Continue Construction of the Restroom Building.
  • Continued Paver Installation at Sandy Springs Circle and Johnson Ferry.
  • Continue Paver Installation at PAC.
  • Continued Installation of Arrival Court Fountain.

Performing Arts Center

  • Continue Hanging Hard Ceilings.
  • Continue Plaster Installation.
  • Continue MEP Overhead Installation at Lobby Level.
  • Continue Installation of Glass/Glazing at VIP lounge.
  • Continue Installation of Ceramic Tile at Restrooms.
  • Continue Installation of Restroom Fixtures and Accessories.
  • Continue Installation of Millwork “Trees” and Wood Caps.
  • Continue Installation of Rigging Materials above stage.

Office Tower & Studio Theatre

  • Continue Metal Panel and Glazing Installation.
  • Continue Roofing Installation at Office Tower.
  • Continue Framing of Hard Lid Ceilings at all levels.
  • Continue Installation of AE04 – AE07 Elevators.
  • Continue Kitchen Equipment Installation.
  • Continue Prime Coat Paint Installation at all levels.
  • Continue Installation of Millwork and Casework.
  • Continue Quartz Countertops Installation at Bathrooms.
  • Continue Tile Installation at Office Tower Lobby.
  • Continue Installation of Navy Island Micro-perf Panels.

CIP Deck

  • Continue East Deck Sprinkler Pipe Installation.
  • Continue Installation of GE01 and GE02 Elevators.
  • Continue PAC and Area G Fountain Room Buildout.
  • Continue Area D Pop up Installation.

Roadways/Utilities

  • Continue Exterior Roads Final Paving.