Construction Activity Update for the Week of March 23, 2018

Construction Activities This Week

Site/Park

  • Commenced Sub-Slab and Paver Installation at Inter-active Fountain.
  • Continued Waterproofing Installation at Waterwall Fountain.
  • Continued Planting at South Parking.
  • Continued Paver Installation at Arcade.
  • Continued Finish Installation at Shade Structures.
  • Continued Roof Terrace Waterwall Installation and Commenced Waterwall Fountain Installation.

Performing Arts Center

  • Continued Installation of PAC Lobby Bar.
  • Continued Final Clean Operations.
  • Continued Completion & Punch List efforts at all levels.

Office Tower & Studio Theatre

  • Completed Flooring Installation at Balance of Lobby Level.
  • Continued Completion & Punch lists at all levels.
  • Continued Final Clean Operations.
  • Verified Punch List Item Completion with Architect.

CIP Deck

  • Continued Skin Element Installation at Pop-Up D.

Construction Activities Next Week

Site/Park

  • Complete Waterproofing Installation at all Fountains.
  • Continue Planting at South Parking.
  • Continue Completion & Punch List efforts.
  • Install Balance of Finishes at All Fountains.
  • Commence Interior Final Pave Operations.

Performing Arts Center

  • Continue Installation of PAC Lobby Bar.
  • Continue Completion & Punch List efforts at all levels.

Office Tower & Studio Theatre

  • Continue Completion & Punch lists at all levels.
  • Coordinate Owner Furniture Move-In at Government Level.
  • Commence Telescopic Seating Installation.

CIP Deck

  • Continue Area D Pop up Installation.