Construction Activity Update for the Week of June 29, 2017

Construction Activity This Week

Site/Park

  • Completed Sidewalk Installation at Fidelity Bank.
  • Continued Construction of the Restroom Building.
  • Continued Installation of Sidewalks at Mt.Vernon Hwy.
  • Continued Construction of Planters at PAC.
  • Continued Waterproofing prep at Waterwall Fountain.

Performing Arts Center

  • Continued Hanging & Finishing Hard Ceilings.
  • Continued Overhead MEP Rough-in at PAC Lobby & Gallery Level.
  • Continued Fire Protection Installation at Gallery Level and Lobby Bar.
  • Continued Plaster Installation.
  • Continued Installation of Glass/Glazing at VIP lounge.
  • Continued Installation of Ceramic Tile at Restrooms.
  • Commenced Installation of Restroom Fixtures.
  • Commenced Installation of Mid-Reflectors.

Office Tower & Studio Theatre

  • Continued Metal Panel Installation.
  • Continued Stair Installation.
  • Continued Chiller and Cooling Tower Start-up.
  • Continued Installation of Glass/Glazing.
  • Continued Roofing Installation at Office Tower.
  • Continued Framing of Hard Lid Ceilings at Service, Lobby, Gallery Levels.
  • Continued Installation of AE03 & AE08 Service Elevators.
  • Continued Exhaust and UDS Install at Kitchen.

CIP Deck

  • Continued East Deck Sprinkler Pipe Installation.
  • Continued East Deck Sprinkler Room Buildout.
  • Continued Point, Patch, and Rub of Columns and Sheer-walls at East Deck.
  • Continued Area G and PAC Fountain Room Buildout.

Roadways/Public Utility

  • Continued JF Stormwork.

Construction Activity Next Week

Site/Park

  • Continue Construction of the Restroom Building.
  • Continue Installation of Sidewalks at Mt.Vernon Hwy.
  • Continue Construction of Planters at PAC.
  • Continue Waterproofing prep at Waterwall Fountain.

Performing Arts Center

  • Continue hanging Hard Ceilings.
  • Continue Overhead MEP Rough-in at PAC Lobby & Gallery Level.
  • Continue Fire Protection Installation at Gallery Level and Lobby Bar.
  • Continue Plaster Installation.
  • Continue MEP Overhead Installation at Lobby Level.
  • Continue Installation of Glass/Glazing at VIP lounge.
  • Continue Installation of Ceramic Tile at Restrooms.
  • Continue Installation of Restroom Fixtures.
  • Continue Installation of Mid-Reflectors.

Office Tower & Studio Theatre

  • Continue Metal Panel Installation.
  • Continue Stair Installation.
  • Continue Chiller and Cooling Tower Start-up.
  • Continue Installation of Glass/Glazing.
  • Continue Roofing Installation at Office Tower.
  • Continue Framing of Hard Lid Ceilings at Service, Lobby, and Gallery Levels.
  • Continue Installation of AE03 & AE08 Service Elevators.
  • Continue Exhaust and UDS Install at Kitchen.

CIP Deck

  • Continue East Deck Sprinkler Pipe Installation.
  • Continue East Deck Sprinkler Room Buildout.
  • Continue Point, Patch, and Rub of Columns and Sheerwalls at East Deck.
  • Continue PAC and Area G Fountain Room Buildout.

Roadways/Utilities

  • Continue JF Stormwork.