Construction Activity Update for the Week of June 15, 2017

Construction Activities This Week

Site/Park

  • Continued Construction of the Restroom Building.
  • Continued Installation of Pumps in the Interactive/ Plaza Fountain Vault.
  • Continued Forming of Planters, Site Walls & Stair at the Shade Bosque.
  • Continued Installation of Sidewalks at Mt.Vernon Hwy.
  • Continued Sidewalk Prep at Fidelity Bank.

Performing Arts Center

  • Continued Hanging & Finishing Hard Ceilings.
  • Continued Overhead MEP Rough-in at PAC Lobby & Gallery Level.
  • Continued Fire Protection Installation at Gallery Level and Lobby Bar.
  • Continued Plaster Installation.
  • Continued Brick Installation at North Elevation.
  • Continued Installation of Glass/Glazing at VIP lounge.
  • Continued Startup of AHU-1 and AHU-6.
  • Continued Installation of Ceramic Tile at Restrooms.

Office Tower & Studio Theatre

  • Continued Metal Panel Installation.
  • Continued Stair Installation.
  • Continued Chiller and Cooling Tower Start-up.
  • Continued Installation of Glass/Glazing.
  • Continued Roofing Installation at Office Tower.
  • Continued Framing of Hard Lid Ceilings at Service, Lobby, Gallery Levels.
  • Continued Installation of AE03 & AE08 Service Elevators.
  • Commenced Exhaust and UDS Install at Kitchen.

CIP Deck

  • Continued East Deck Sprinkler Pipe Installation.
  • Continued East Deck Sprinkler Room Buildout.
  • Continued Point, Patch, and Rub of Columns and Sheer-walls at East Deck.
  • Continued PAC Fountain Room Buildout.

Roadways/Public Utility

  • Continued SSC West Storm Drainage work.
  • Continued GA Power Jack & Bore at Roswell Rd.

Construction Activities Next Week

Site/Park

  • Continue Restroom Building CMU Installation.
  • Continue Installation of Pumps in the Interactive/Plaza Fountain Vault.
  • Continue Waterproofing of the PAC Fountain.
  • Continue Forming of Planters, Site Walls & Stair at the Shade Bosque.
  • Continue Installation of Sidewalks at Mt. Vernon Hwy.
  • Continue Sidewalk Installation at Fidelity Bank.

Performing Arts Center

  • Continue hanging Hard Ceilings.
  • Continue Overhead MEP Rough-in at PAC Lobby & Gallery Level.
  • Continue Fire Protection Installation at Gallery Level and Lobby Bar.
  • Continue Plaster Installation.
  • Continue MEP Overhead Installation at Lobby Level.
  • Continue Installation of Glass/Glazing at VIP lounge.
  • Continue Startup of AHU-1 and AHU-6.
  • Continue Installation of Ceramic Tile at Restrooms.

Office Tower & Studio Theatre

  • Continue Metal Panel Installation.
  • Continue Stair Installation.
  • Continue Chiller and Cooling Tower Start-up.
  • Continue Installation of Glass/Glazing.
  • Continue Roofing Installation at Office Tower.
  • Continue Framing of Hard Lid Ceilings at Service, Lobby, and Gallery Levels.
  • Continue Installation of AE03 & AE08 Service Elevators.
  • Continue Exhaust and UDS Install at Kitchen.

CIP Deck

  • Continue East Deck Sprinkler Pipe Installation.
  • Continue East Deck Sprinkler Room Buildout.
  • Continue Point, Patch, and Rub of Columns and Sheerwalls at East Deck.
  • Continue PAC Fountain Room Buildout.

Roadways/Utilities

  • Complete Sandy Springs West Stormwork.
  • Commence Johnson Ferry Stormwork.