Construction Activity Update for the Week of December 7, 2017

Construction Activities This Week

Site/Park

  • Completed Installation of Sidewalks at Mt. Vernon Hwy.
  • Continued Exterior Skin Installation at the Restroom Building.
  • Continued Paver Installation at Mt. Vernon Hwy, Johnson Ferry and PAC.
  • Continued Waterproofing Installation at Arrival Court Fountain.
  • Continued Installation of Trees at the Park.
  • Continued Curb & Gutter Installation at South Parking.

Performing Arts Center

  • Continued Installation of Hunter Douglass Ceiling.
  • Continued Installation of Restroom Fixtures and Accessories.
  • Continued Installation of Millwork “Trees” and Wood Caps.
  • Continued Installation of Rigging Materials above stage.
  • Continued Seating Installation.
  • Continued Flooring Installation at Stage.
  • Continued Tile Installation at the Lobby.

Office Tower & Studio Theatre

  • Continued Metal Panel and Glazing Installation.
  • Continued Installation of AE04 – AE07 Elevators.
  • Continued Kitchen Equipment Installation.
  • Continued Installation of Millwork and Casework.
  • Continued Quartz Countertops Installation at Bathrooms.
  • Continued Carpet Installation at Office Tower.
  • Continued Glass Door Installation.
  • Continued Installation of Navy Island Micro-perf Panels.
  • Continued Installation of Pedestal Pavers at Roof Terrace.

CIP Deck

  • Continued Area D Pop up Installation.
  • Continued Area E Pop up Installation.
  • Continued Striping.

Construction Activities Next Week

Site/Park

  • Continue Exterior Skin Installation at the Restroom Building.
  • Continue Paver Installation at Mt. Vernon Hwy, Johnson Ferry and PAC.
  • Continue Waterproofing Installation at Arrival Court Fountain.
  • Continue Installation of Trees at the Park.
  • Continue Curb & Gutter Installation at South Parking.

Performing Arts Center

  • Continue Installation of Hunter Douglass Ceiling.
  • Continue Installation of Restroom Fixtures and Accessories.
  • Continue Installation of Millwork “Trees” and Wood Caps.
  • Continue Installation of Rigging Materials above stage.
  • Continue Seating Installation.
  • Continue Flooring Installation at Stage.
  • Continue Tile Installation at the Lobby.

Office Tower & Studio Theatre

  • Continue Metal Panel and Glazing Installation.
  • Continue Installation of AE04 – AE07 Elevators.
  • Continue Kitchen Equipment Installation.
  • Continue Installation of Millwork and Casework.
  • Continue Quartz Countertops Installation at Bathrooms.
  • Continue Carpet Installation at Office Tower.
  • Continue Glass Door Installation.
  • Continue Installation of Navy Island Micro-perf Panels.
  • Continue Installation of Pedestal Pavers at Roof Terrace.

CIP Deck

  • Continue Area D Pop up Installation.
  • Continue Area E Pop up Installation.
  • Continue Striping.