Construction Activities This Week
Site/Park
- Continued Exterior Skin Installation at the Restroom Building.
- Continued Paver Installation at Mt. Vernon Hwy, Johnson Ferry and PAC.
- Continued Waterproofing Installation at Arrival Court Fountain.
- Continued Installation of Trees at the Park.
- Continued Curb & Gutter Installation at South Parking.
Performing Arts Center
- Completed Seating Installation.
- Continued Installation of Hunter Douglass Ceiling.
- Continued Installation of Restroom Fixtures and Accessories.
- Continued Installation of Millwork “Trees” and Wood Caps.
- Continued Installation of Rigging Materials above stage.
- Continued Flooring Installation at Stage.
- Continued Tile Installation at the Lobby.
- Continued Installation of the Bar.
- Continued AV Installation.
Office Tower & Studio Theatre
- Continued Metal Panel and Glazing Installation.
- Continued Installation of AE01-AE07 Elevators.
- Continued Kitchen Equipment Installation.
- Continued Installation of Millwork and Casework.
- Continued Quartz Countertops Installation at Bathrooms.
- Continued Carpet Installation at Office Tower.
- Continued Glass Door Installation.
- Continued Installation of Navy Island Micro-perf Panels.
- Continued Installation of Pedestal Pavers at Roof Terrace.
- Continued AV Installation.
- Continued Installation of Fabric Wall Panels.
CIP Deck
- Continued Area D Pop up Installation.
- Continued Area E Pop up Installation.
- Continued Striping.
Construction Activities Next Week
Site/Park
- Continue Exterior Skin Installation at the Restroom Building.
- Continue Paver Installation at Mt. Vernon Hwy, Johnson Ferry and PAC.
- Continue Waterproofing Installation at Arrival Court Fountain.
- Continue Installation of Trees at the Park.
- Continue Curb & Gutter Installation at South Parking.
Performing Arts Center
- Continue Installation of Hunter Douglass Ceiling.
- Continue Installation of Restroom Fixtures and Accessories.
- Continue Installation of Millwork “Trees” and Wood Caps.
- Continue Installation of Rigging Materials above stage.
- Continue Flooring Installation at Stage.
- Continue Tile Installation at the Lobby.
- Continue Installation of the Bar.
- Continue AV Installation.
Office Tower & Studio Theatre
- Continue Metal Panel and Glazing Installation.
- Continue Installation of AE01-AE07 Elevators.
- Continue Kitchen Equipment Installation.
- Continue Installation of Millwork and Casework.
- Continue Quartz Countertops Installation at Bathrooms.
- Continue Carpet Installation at Office Tower.
- Continue Glass Door Installation.
- Continue Installation of Navy Island Micro-perf Panels.
- Continue Installation of Pedestal Pavers at Roof Terrace.
- Continue AV Installation.
- Continue Installation of Fabric Wall Panels.
CIP Deck
- Continue Area D Pop up Installation.
- Continue Area E Pop up Installation.
- Continue Striping.