Construction Activity Update for the Week of April 5, 2018

Construction Activities This Week

Site/Park

  • Continued Waterproofing Installation at Waterwall Fountain.
  • Continued Planting at South Parking.
  • Continued Installation of Roof Terrace Waterwall Fountain.
  • Continued Interior Final Pave Operations.
  • Continued Paving at South Parking.

Performing Arts Center

  • Continued Installation of PAC Lobby Bar.
  • Continued Completion & Punch List efforts at all levels.
  • Continued Final Clean Operations.
  • Continued Curtain Installation.

Office Tower & Studio Theatre

  • Continued Flooring Installation at Lobby Level.
  • Continued Completion & Punch lists at all levels.
  • Coordinated Owner Furniture Move In at Government Level.
  • Coordinated Owner Furniture Move In at Tenant Level.
  • Hang Curtains at Studio Theater.
  • Finish Telescopic Seating Installation.

CIP Deck

  • Continued Area D Pop up Installation.

Construction Activities Next Week

Site/Park

  • Continue Waterproofing Installation at Waterwall Fountain.
  • Continue Planting at South Parking.
  • Continue Installation of Roof Terrace Waterwall Fountain.

Performing Arts Center

  • Continue Installation of PAC Lobby Bar.
  • Continue Completion & Punch List efforts at all levels.
  • Continue Final Clean Operations.

Office Tower & Studio Theatre

  • Continue Flooring Installation at Lobby Level.
  • Continue Completion & Punch lists at all levels.
  • Coordinate Owner Furniture Move In at Tenant and Level.
  • Theatrical Testing at Studio Theater.

CIP Deck

  • Continue Area D Pop up Installation.