Construction Activity for the week of October 6, 2016

Construction Activities This Week

Site/Structure

  • Completed Installation of Grease traps at the Fidelity Bank Site.
  • Continued Installation of Hardscape Mockup.
  • Commenced Installation of the Storm Trap System (Irrigation Cistern)
  • Commenced Installation of French Drain at the Perimeter of Area D.

Performing Arts Center

  • Completed Installation of the Main Steel Structures at the PAC Theatre & Seating Area.
  • Continued Architectural Precast Prep for the North Elevation.
  • Continued forming of North and South Stairs.
  • Commenced Installation of Catwalks and Grating for the Main Trusses at Area C2.

Office Tower & Studio Theatre

  • Completed Installation of Area A3 Gallery Level.
  • Continued Installation of B1 Studio Theatre Conference Level.
  • Commenced Forming of A3/A4/A5 Office Tower Conference Level.

CIP Deck

  • Completed Installation of Area D3 Lid Level.
  • Continued Forming of Area D4 Lid Level.
  • Continued Fire Protection Installation.
  • Commenced Installation of Area E1 Elevated Slab A1/ A2 Level.
  • Commenced Waterproofing Installation at Area D1 Lid Level.

Roadways

  • Continue grading along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continue Storm Structure Installation along Mt. Vernon Hwy.
  • Completed removal of all utility lines off the poles along Sandy Springs Circle.

Other

  • Continued Georgia Power Trenching at Roswell Road.

Construction Activities Next Week

Site/Structure

  • Complete Installation of Hardscape Mockup.
  • Complete Installation of the Storm Trap System (Irrigation Cistern)
  • Commence Installation of Grease Traps North of Office Tower.
  • Continued Installation of French Drain at the Perimeter of Area D.

Performing Arts Center

  • Continue Installation of North and South Stairs.
  • Continue Overhead Plumbing and Electrical Line layout at Lobby Bar.
  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Commence Concrete Installation of PAC Roof at Area C1.
  • Commence Installation of Steel Structure at the PAC Flyloft level Area C3.

Office Tower & Studio Theatre

  • Complete Installation of B1 Studio Theatre Conference Level.
  • Continued Forming and Reinforcing of A3/A4/A5 Office Tower Conference Level.
  • Commence Removal of Reshores at Area B1 & B2 Studio Theater Lobby Level.

CIP Deck

  • Complete Installation of Area D4 Lid Level.
  • Continue Fire Protection Installation.
  • Continued Installation of Area E1 Elevated Slab A1/A2 Level.
  • Continued Installation of Waterproofing at Area D Lid Level.

Roadways

  • Continue grading along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continue Storm Structure Installation along Mt. Vernon Hwy.

Other

  • Continue Georgia Power Trenching at Roswell Road.