  • Continue Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Continued Raker Beam Re-Steel Installation.
  • Completed Elevator CE-01 3rd lift Wall Installation.
  • Continued Area B1 Studio Theatre Foundations & Columns.
  • Commenced Re-steel installation on South Lobby level slab.

Building

  • Continued Re-Steel & Installation of O8 Line Structural Wall.
  • Continued Installation of Continuous Footings at Office Tower.
  • Commenced Slab on Grade Prep.

Parking Deck

  • Poured & Stressed Tendons in Area G1 Lid.
  • Continued Slab-On-Grade Prep/Excavation In Cast-In-Place Deck.
  • Completed Area G2 Lid Level Formwork & Re-Steel installation at Cast-In-Place-Deck.
  • Commenced Area G3 Lid Formwork.
  • Completed Mid-level Column installation in Area G3.
  • Continued Area F Footer Installation.

Roadways

  • Continue Grading of Mt.Vernon and Sandy Springs Intersection.
  • Commenced Curb Installation Along Mt. Vernon.
  • Continued Installation of Storm line piping.
  • Continued Installation of Bluestone Rd.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Continue Precast Deck – Topping Slab Installation

Next Week’s Construction Activities

Site/Structure

  • Continue Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Pour Raker Beams at Balcony Level
  • Complete Installation of Area C5 Continuous Footing.
  • Continue Area B1 Studio Theatre Foundations & Columns
  • Commence Re-steel installation on South Lobby level Slab.

Building

  • Continue Re-Steel & Installation of O8 Line Structural Wall.
  • Continue Installation of Continuous Footings at Office Tower.
  • Continue Slab on Grade Prep.

Parking Deck

  • Continue Slab-On-Grade Prep/Excavation In Cast-In-Place Deck
  • Complete Area G2 Lid Level Concrete Pour at Cast-In-Place deck.
  • Commence Area G3 Lid Re-Steel Installation.
  • Continue Footing Installation in Area F
  • Commence Lid Waterproofing Are H1

Roadways

  • Continue Grading of Mt.Vernon and Sandy Springs Intersection.
  • Continue Curb Installation Along Mt. Vernon
  • Continue Installation of Bluestone Rd.

Other

  • Continue Georgia Power Trenching at Mount Vernon NWY NE.
  • Continue Precast Deck – Topping Slab Installation