Construction Activities for the week of June 2, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Poured Raker Beams at Balcony Level
  • Completed Installation of Area C5 Continuous Footing & Walls.
  • Continued Area B1 Studio Theatre Foundations & Columns
  • Commenced Re-steel installation on South Lobby Level Slab.
  • Completed Formwork C6 Lobby Level and Began Rebar, prep and pour.

Building

  • Continued Re-Steel & Installation of O8 Line Structural Wall.
  • Continued Installation of Continuous Footings at Studio Theatre.

Parking Deck

  • Completed Area G2 Lid Level Concrete Pour at Cast-In-Place deck.
  • Commenced Area G3 Lid Re-Steel Installation.
  • Continued Footing Installation in Area F
  • Commenced Lid Waterproofing Area H1

Roadways

  • Continued Grading of Mt.Vernon and Sandy Springs Intersection.
  • Continued Curb Installation Along Mt. Vernon
  • Continued Installation of Bluestone Rd.
  • Poured Retaining Wall & Footing at Fidelity Bank.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Continued Precast Deck – Topping Slab Installation

Next Week’s Construction Activities

Site/Structure

  • Continue Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Complete Re-Steel & Pour of South Lobby Level Elevated Slab
  • Commence Elevator C:E001 Pit Pour.
  • Continue Area B1 Studio Theatre Columns & Walls.
  • Complete Trap Level CMU Block Installation.
  • Begin Elevated Formwork at Lobby Level East of Balcony

Building

  • Continue Re-Steel & Installation of O8 Line Structural Wall.
  • Continue Installation of Continuous Footings at Office Tower.
  • Continue Installation of Walls and Columns at Studio Theatre.

Parking Deck

  • Complete Area G3 Lid Level Concrete Pour at Cast-In-Place deck.
  • Commence Area G4 & G5 Lid Re-Steel Installation.
  • Continue Footing & Column Installation in Area F
  • Commence Lid Waterproofing Area H2

Roadways

  • Continue Grading of Mt.Vernon and Sandy Springs Intersection.
  • Complete Curb Installation at Mt. Vernon Sandy Springs Intersection.
  • Continue Installation of Bluestone Rd.
  • Commence Fidelity Bank Stone Wall Installation.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE.
  • Continue Precast Deck – Topping Slab Installation