Construction Activities for the week of June 16, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Commenced Re-Steel Installation at Gallery Level Balcony.
  • Commenced Formwork installation 3rd lift on WA Wall—West Stage.
  • Completed Formwork & Re-Steel Installation of North Balcony Wall 3rd lift.
  • Continued CIP Footing, Column, & Wall Installation at Studio Theatre.

Office Tower

  • Continued Re-Steel & Installation of Foundation Structural Wall Adjacent to 08 Line Wall.
  • Commenced Installation of Continuous Footings at Office Tower.
  • Commenced Installation of Elevators AE01 & AE02Elevator Pit.

Parking Deck

  • Completed Area G4 & G5 Lid Level Concrete Pour at Cast-In-Place deck & Stressed Tendons.
  • Continued Footing & Column Installation in Area F.
  • Continued Waterproofing on Lid.

Roadways

  • Completed Striping of Mt. Vernon / Sandy Springs Intersection.
  • Opened Mt. Vernon/ Sandy Springs Intersection to public as a three direction intersection— Mt. Vernon East of the Intersection closed.
  • Continued Grading along Mt. Vernon.
  • Continued Installation of Bluestone Rd.
  • Continue Fidelity Bank Retaining Wall Installation.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Continued Precast Deck – Topping Slab Installation.

Next Week’s Construction Activities

Site/Structure

  • Continue Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Complete Re-Steel Installation at Gallery Level Balcony.
  • Commenced Re-Steel installation 3rd lift on WA Wall – West Stage.
  • Continue Formwork & Re-Steel Installation of North Balcony Wall 3rd lift.
  • Complete CIP Footing, Column, & Wall Installation at Studio Theatre.
  • Commence Slab on Grade Prep in the Studio Theatre.

Office Tower

  • Complete Re-Steel & Installation of Foundation Structural Wall Adjacent to 08 Line Wall.
  • Continue Installation of Continuous Footings at Office Tower.
  • Continue Installation of Elevators AE01 & AE02 ElevatorPit.

Parking Deck

  • Complete South Electrical Room — Area G2 & G3.
  • Complete Footing & Column Installation in Area F.
  • Commence Slab on Grade Prep – Area F.
  • Continue Waterproofing on Lid.

Roadways

  • Continued Underground Utility work on Mt. Vernon working East.
  • Continue Grading along Mt. Vernon—Continuing East.
  • Continue Installation of Bluestone Rd.
  • Complete House Demo Along Hildebrand.
  • Commence Fidelity Bank Retaining Wall Installation.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE.
  • Continue Precast Deck – Topping Slab Installtion.