Construction Activities for the week of September

Construction Activities This Week

Site/Structure

  • Continued Installation of Grease traps at the Fidelity Bank Site.
  • Continued Excavation and Installation of Shoring Walls for the Construction of the Irrigation Cistern.
  • Continued Installation of Hardscape Mockup.

Performing Arts Center

  • Continued Installation of Foundations at PAC Area C7.
  • Continued Structural Steel Installation at PAC Stage.
  • Continued forming of North and South Stairs.
  • Commence Architectural Precast Prep for the North Elevation.

Office Tower & Studio Theatre

  • Completed Installation of Column and Walls at Area A3 Lobby Level.
  • Continued Column Installation from Gallery Level to Conference Level.
  • Continued to Form and Reinforce Area A2 Gallery Level.
  • Continued Backfill of Retail – Area A3.
  • Completed Installation of Area B1 & A1 Gallery Level Elevated Slab.
  • Continued Waterproofing and Backfill of 01-Line Walls.

CIP Parking Deck

  • Completed Installation of Area D1 A1/A2 Level.
  • Completed Installation of Area D2 A1/A2 Level.
  • Completed Installation of Area D Ramp SOG.
  • Continued Fire Protection Installation.
  • Continued to form and Reinforce Area D1 Lid.
  • Continued Column Installation from A1/A2 Level to Lid Area D.

Roadways

  • Continued Retaining Wall Installation at Mt. Vernon Hwy / Sandy Springs Circle.
  • Continued Grading along Mt. Vernon Hwy. (Phase 3—Chase Bank)
  • Continued Storm Structure Installation along Mt. Vernon Hwy.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE and Roswell Road

Next Week’s Construction Activities

Site/Structure

  • Complete Installation of Grease traps at the Fidelity Bank Site.
  • Complete Installation of Hardscape Mockup.
  • Continue Excavation and Installation of Shoring Walls for the Construction of the Irrigation Cistern.

Performing Arts Center

  • Complete SOG Installation of Foundations at PAC Area C7.
  • Continue Installation of the Steel Structure at Area C1.
  • Continue Architectural Precast Prep for the North Elevation.

Office Tower & Studio Theatre

  • Complete all Column Installation from Lobby Level to Gallery Level.
  • Complete Installation of Area A2 Gallery Level.
  • Complete Waterproofing and Backfill of 01-Line Walls.
  • Continue to Form and Reinforce Area A3 Gallery Level.
  • Commence Forming of B1 Studio Theatre Roof Level.

CIP Parking Deck

  • Continue Installation of Area D1 Lid.
  • Continue Fire Protection Installation.
  • Commence Forming and Reinforcing of Area D2 & D3 Lid Level.

Roadways

  • Complete Retaining Wall Installation at Mt. Vernon Hwy / Sandy Springs Circle.
  • Continue Grading along Mt. Vernon Hwy. (Phase 3—Chase Bank)
  • Continued Storm Structure Installation along Mt. Vernon Hwy.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE and Roswell Road