Construction Activities for the week of September 29, 2016

Construction Activities This Week

Site/Structure

  • Completed Subgrade Prep for the Construction of the Irrigation Cistern.
  • Completed Installation of Grease traps at the Fidelity Bank Site.
  • Continued Installation of Hardscape Mockup.

Performing Arts Center

  • Completed Structural Steel Installation at PAC Stage Area C1.
  • Commenced Installation of Steel Structure at the PAC Theatre & Seating Area.
  • Continued forming of North and South Stairs.
  • Continued Architectural Precast Prep for the North Elevation.

Office Tower & Studio Theatre

  • Completed all Column Installation from Gallery Level to Conference Level.
  • Completed Waterproofing and Backfill of 01-Line Walls.
  • Continued forming and reinforcing of A3 Gallery Level.
  • Continued Forming of B1 Studio Theatre Roof Level.

CIP Deck

  • Completed Installation of Area D1/D2 Lid.
  • Completed Column Installation from A1/A2 Level to Lid Area D.
  • Continued Fire Protection Installation.
  • Continued forming of Area D3/D4 Lid.

Roadways

  • Completed paving along Mt. Vernon Hwy. (Phase 3—Chase Bank)
  • Completed removal of all utility lines off the poles along Sandy Springs Circle.
  • Continued grading along Mt. Vernon Hwy. (Phase 2—Central Portion)

Other

  • Completed Georgia Power Trenching and Duct bank remediation at Mount Vernon HWY.
  • Continued Georgia Power Trenching at Roswell Road.

Construction Activities Next Week

Site/Structure

  • Continue Installation of Hardscape Mockup.
  • Commence Installation of the Precast Panels for the Irrigation Cistern.
  • Commence Installation of Grease Traps North of Office Tower.

Performing Arts Center

  • Complete forming of North and South Stairs.
  • Complete Concrete Installation of PAC Roof at Area C1.
  • Continue Installation of Steel Structure at the PAC Theatre & Seating Area.
  • Continue Architectural Precast Prep for the North Elevation.

Office Tower & Studio Theatre

  • Complete Installation of Area A3 Gallery Level.
  • Complete Installation of B1 Studio Theatre Roof Level.
  • Commence Forming and Reinforcing of A3/A4/A5 Office Tower Conference Level.

CIP Deck

  • Complete Installation of Area D3 Lid Level.
  • Continue Fire Protection Installation.
  • Continue forming of Area D4 Lid Level.

Roadways

  • Continue grading along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continue Storm Structure Installation along Mt. Vernon Hwy.

Other

  • Continue Georgia Power Trenching at Roswell Road.