Construction Activities for the week of September 22, 2016

Construction Activities This Week

Site/Structure

  • Completed Excavation and Installation of Shoring Walls for the Construction of the Irrigation Cistern.
  • Continued Installation of Grease traps at the Fidelity Bank Site.
  • Continued Installation of Hardscape Mockup.

Performing Arts Center

  • Completed SOG Installation at PAC Area C7.
  • Continued Structural Steel Installation at PAC Stage.
  •  Continued forming of North and South Stairs.
  • Continued Architectural Precast Prep for the North Elevation.

Office Tower & Studio Theatre

  • Completed Installation of A2 Gallery Level.
  • Continued Column Installation from Gallery Level to Conference Level.
  • Continued to Form and Reinforce A3 Gallery Level.
  • Completed Backfill of Retail – Area A3.
  • Continued Waterproofing and Backfill of 01-Line Walls.
  • Commence Forming of B1 Studio Theatre Roof Level.

CIP Parking Deck

  • Continued Fire Protection Installation.
  • Completed forming and reinforcing of Area D1 Lid.
  • Continued Column Installation from A1/A2 Level to Lid Area D.
  • Continued forming of Area D2/D3 Lid.

Roadways

  • Completed Retaining Wall Installation at Mt. Vernon Hwy / Sandy Springs Circle.
  • Continued Storm Structure Installation along Mt. Vernon Hwy.
  • Commenced paving along Mt. Vernon Hwy. (Phase 3—Chase Bank).

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE and Roswell Road.

Construction Activities Next Week

Site/Structure

  • Complete Installation of Grease traps at the Fidelity Bank Site.
  • Continue Installation of Hardscape Mockup.
  • Commence subgrade preparation for the Irrigation Cistern.

Performing Arts Center

  • Continue Installation of the Steel Structure at Area C1.
  • Continue Architectural Precast Prep for the North Elevation.
  • Complete forming of North and South Stairs.
  • Commence Installation of Steel Structure at the PAC Theatre & Seating Area.

Office Tower & Studio Theatre

  • Complete all Column Installation from Gallery Level to Conference Level.
  • Complete Waterproofing and Backfill of 01-Line Walls.
  • Continue to Form and Reinforce Area A3 Gallery Level.
  • Continue Forming of B1 Studio Theatre Roof Level.

CIP Parking Deck

  • Continue Installation of Area D2 Lid.
  • Continue Fire Protection Installation.
  • Commence Forming of Area D3/D4 Lid Level.

Roadways

  • Continue paving along Mt. Vernon Hwy. (Phase 3—Chase Bank).
  • Continue Storm Structure Installation along Mt. Vernon Hwy.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE and Roswell Road.