Construction Activities for the week of September 1, 2016

Construction Activities This Week

Site/Structure

  • Completed Dirt Ramp removal in to CIP Deck.
  • Completed Installation of the G2 Structure along Market Square.
  • Completed Southwest Retaining Wall Construction.
  • Continued Installation of Grease traps at the Fidelity Bank Site.
  • Commenced Installation of Shoring Walls for the construction of the Irrigation Cistern.

Performing Arts Center

  • Completed Installation of all Stage Walls and Proscenium Walls.
  • Continued Forming C6 Roof.
  • Continued to Form and Reinforce WA Wall.
  • Continued to Form and Reinforce Area C2 at the Flyloft Level.
  • Commence Installation on Foundations at PAC Area C7.

Office Tower & Studio Theatre

  • Completed Installation of A2 & A3 Lobby Level.
  • Completed Installation of all Footings.
  • Continued Column Installation at Area B1, A1 & A2.

CIP Parking Deck

  • Continued Slab on Grade at Area D.
  • Completed Area E Under-Drainage Installation.
  • Continued to Form and Reinforce Elevated Slab at Area D1 Mid Deck.
  • Continued Fire Protection Installation.
  • Commence Area E Slab on Grade Prep.

Roadways

  • Completed Phase 1 of Paving at Bluestone Rd & Mt. Vernon Hwy.
  • Shift Site Entrance to Mt. Vernon Hwy. and Bluestone Rd.

Other

  • Continued Georgia POwer Trenching at Mount Vernon HWY NE and Roswell Road.

Construction Activities Next Week

Site/Structure

  • Complete Installation of Grease traps at the Fidelity Bank Site.
  • Complete Installation of SS-16.
  • Continue Installation of Shoring Walls for the construction of the Irrigation Cistern.

Performing Arts Center

  • Continue WA Wall Installation—West Stage.
  • Continue Forming/Topping out of the Northeast Walls.
  • Continue Forming C6 Roof.
  • Continued to Form and Reinforce Area C2 at the Flyloft Level.
  • Commence Installation of the Steel Structure at Area C1.

Office Tower & Studio Theatre

  • Continue Column Installation at Area A2 & A3.
  • Continue to Form and Reinforce Area B1 & A1 Gallery Level Elevated Slab.
  • Continue to Form and Reinforce Area A3 Conference Level.

CIP Parking Deck

  • Complete Installation of Area D1 Elevated Slab.
  • Complete Slab on Grade Installation at Area E.
  • Continue Fire Protection Installation.
  • Commence Forming and Reinforcing of Area D2 Elevated Slab.

Roadways

  • Complete Curb & Gutter Installation for Phase 1 of Mt. Vernon and Bluestone Rd.
  • Continue Underground Utility work on Mt. Vernon working East.
  • Continue grading along Mt. Vernon Hwy.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE and Roswell Road.