Construction Activities for the week of September 08, 2016

Construction Activities This Week

Site/Structure

  • Completed Underslab Drainage Installation at Area E.
  • Continued Installation of Grease traps at the Fidelity Bank Site.
  • Continued Excavation and Installation of Shoring Walls for the Construction of the Irrigation Cistern.

Performing Arts Center

  • Completed Installation of all Stage Walls and Proscenium Walls.
  • Completed Installation of C6 Roof.
  • Completed Installation of WA Wall.
  • Commenced Installation of Foundations at PAC Area C7.
  • Commenced Structural Steel Installation at PAC Stage.

Office Tower & Studio Theatre

  • Continued Column Installation at Area B1, A2 & A3.
  • Continued to Form and Reinforce Area B1 & A1 Gallery Level Elevated Slab.
  • Continued to Form and Reinforce Area A3 Gallery Level.
  • Commenced Forming and Reinforcing of Walls and Columns at Area A3 Lobby Level.
  • Commenced Waterproofing and Backfill of 01-Line Walls.

CIP Parking Deck

  • Completed Installation of Area D1 A1/B1 Level.
  • Continued Fire Protection Installation.
  • Poured Area E Slab on Grade.
  • Commenced Forming and Reinforcing of Area D2 A1/ B1 Level
  • Began Area D1 Lid Formwork.

Roadways

  • Completed Waterline Installation along Mt. Vernon Hwy.
  • Continued Retaining Wall Installation at Mt. Vernon Hwy / Sandy Springs Circle.
  • Continued Grading along Mt. Vernon Hwy. (Phase 3—Chase Bank)

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE and Roswell Road

Construction Activities Next Week

Site/Structure

  • Complete Installation of Grease traps at the Fidelity Bank Site.
  • Continue Excavation and Installation of Shoring Walls for the Construction of the Irrigation Cistern.
  • Commence Installation of Storm lines at the South Side off the site along Mt. Vernon Hwy.

Performing Arts Center

  • Commence Installation of Foundations at PAC Area C7.
  • Continue Installation of the Steel Structure at Area C1.
  • Commence Architectural Precast Prep for the North Elevation.

Office Tower & Studio Theatre

  • Complete all Column Installation from Lobby Level to Gallery Level.
  • Complete Installation of Area B1 Gallery Level Elevated Slab.
  • Continue to Form and Reinforce Area A2 Gallery Level.
  • Continue Waterproofing and Backfill of 01-Line Walls.
  • Continue Backfill of Retail – Area A3.

CIP Parking Deck

  • Continue Fire Protection Installation.
  • Continue Forming and Reinforcing of Area D2 Elevated Slab.
  • Continue Forming and Reinforcing of Area D1 A1/B1 Slab.

Roadways

  • Continue grading along Mt. Vernon Hwy.
  • Complete Waterline Installation along Mt. Vernon Hwy.
  • Continue Retaining Wall Installation at Mt. Vernon Hwy / Sandy Springs Circle.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE and Rosell Road