Construction Activities for the week of October 27, 2016

Construction Activities This Week

Site/Structure

  • Continued Backfill of the Storm Trap System (Irrigation Cistern)
  • Continued Installation of Grease Traps North of Office Tower.

Performing Arts Center

  • Continued Installation of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C1 & C2.
  • Continued Architectural Precast Installation at the North Elevation.
  • Continued Overhead Plumbing and Electrical Line layout at Lobby Bar.

Office Tower & Studio Theatre

  • Complete Installation of A3/A4/A5 Office Tower Conference Level.
  • Continued Removal of Reshores at Area B1 & B2 Studio Theater Lobby Level.
  • Commenced Formwork for Area A1 & A2 Conference Level.

CIP Deck

  • Complete all Installation of A1/A2 Levels in the Parking Deck.
  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area D Lid Level.
  • Continue Forming and Reinforcing of Area E1 Lid Level.
  • Continue Installation of the North Notch.
  • Commence Forming of Area E2 Lid Level.

Roadways

  • Continued grading along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continued Storm Structure Installation along Mt. Vernon Hwy.

Other

  • Continued Georgia Power Trenching at Roswell Road

Construction Activities Next Week

Site/Structure

  • Complete Installation of Grease Traps North of Office Tower.
  • Complete Backfill of the Storm Trap System (Irrigation Cistern)
  • Commence Utility Line Installation to the Performance Art Theatre.
  • Commence Slip Ramp Excavation and Shoring Wall Installation.

Performing Arts Center

  • Continue SOG prep for North and South Stairs.
  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C1& C2.
  • Continue Architectural Precast Installation at the  North Elevation.
  • Continue Overhead Plumbing and Electrical Line layout at Lobby Bar.

Office Tower & Studio Theatre

  • Complete Removal of Reshores at Area B1 & B2 Studio Theater Lobby Level.
  • Complete Installation of Area A1 & A2 Conference Level.
  • Commence Forming of Area A1 Tenant Level.

CIP Deck

  • Complete Installation of North Notch.
  • Complete Installation of Area E1 Lid Level.
  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area D Lid Level.
  • Commence Forming & Reinforcing of Area E2 Lid Level.

Roadways

  • Commence paving along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continue Storm Structure Installation along Mt.Vernon Highway

Other

  • Continue Georgia Power Trenching at Roswell Road