  • Continued Backfill of the Storm Trap System (Irrigation Cistern)
  • Continued Installation of Grease Traps North of Office Tower.
  • Completed Installation of French Drain at the Perimeter of Area D.

Performing Arts Center

  • Continued Installation of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C1 & C2.
  • Commenced Architectural Precast Installation at the North Elevation.
  • Commenced Overhead Plumbing and Electrical Line layout at Lobby Bar.

Office Tower & Studio Theatre

  • Continued Forming and Reinforcing of A3/A4/A5 Office Tower Conference Level.
  • Commenced Removal of Reshores at Area B1 & B2 Studio Theater Lobby Level.
  • Commenced Formwork for Area A1 Conference Level.

CIP Deck

  • Complete Installation of Area E A1/A2 Level.
  • Complete Installation of Area F1 Elevated Slab A1/A2 Level.
  • Continue Forming and Reinforcing of Area F2 A1/A2Level.
  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area D Lid Level.
  • Commence Area E1 Lid Level Formwork.

Roadways

  • Continued grading along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continued Storm Structure Installation along Mt. Vernon HWY

Other

  • Continued Georgia Power Trenching at Roswell Road

Construction Activities Next Week

Site/Structure

  • Complete Installation of Grease Traps North of Office Tower.
  • Complete Backfill of the Storm Trap System (Irrigation Cistern)

Performing Arts Center

  • Continue SOG prep for North and South Stairs.
  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C1& C2.
  • Continue Architectural Precast Installation at the North Elevation.
  • Commence Overhead Plumbing and Electrical Line layout at Lobby Bar.

Office Tower & Studio Theatre

  • Continue Forming of A3/A4/A5 Office Tower Conference Level.
  • Continue Formwork & Reinforcing of Area A1 Conference Level.
  • Continue Removal of Reshores at Area B1 & B2 Studio Theater Lobby Level.
  • Commence Forming of Area A2 Conference Level.

CIP Deck

  • Complete Installation of North Notch.
  • Complete Installation of Area F2 A1/A2 Level.
  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area D Lid Level.
  • Continue Forming & Reinforcing of Area E1 Lid Level.

Roadways

  • Commence paving along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continue Storm Structure Installation along Mt. Vernon HWY

Other

  • Continue Georgia Power Trenching at Roswell Road