Construction Activities for the week of October 13, 2016

Construction Activities This Week

Site/Structure

  • Completed Installation of the Storm Trap System (Irrigation Cistern)
  • Continued Installation of Hardscape Mockup.
  • Continued Installation of French Drain at the Perimeter of Area D.
  • Commenced Installation of Grease Traps North of Office Tower.

Performing Arts Center

  • Continued Architectural Precast Prep for the East Elevation.
  • Continued forming of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C2.

Office Tower & Studio Theatre

  • Complete Installation of B1 Studio Theatre Conference Level.
  • Continued Forming of A3/A4/A5 Office Tower Conference Level.

CIP Deck

  • Completed Installation of Area D4 Lid Level.
  • Continued Fire Protection Installation.
  • Continued forming of Area E1 & F1 Elevated Slab A1/ A2 Level.
  • Continued Waterproofing Installation at Area D1/D2 Lid Level.

Roadways

  • Continued grading along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continued Storm Structure Installation along Mt. Vernon Hwy.

Other

  • Continued Georgia Power Trenching at Roswell Road.

Construction Activities Next Week

Site/Structure

  • Complete Installation of Hardscape Mockup.
  • Continue Installation of Grease Traps North of Office Tower.
  • Continue Installation of French Drain at the Perimeter of Area D.
  • Commence Backfill of the Storm Trap System (Irrigation Cistern)

Performing Arts Center

  • Continue Installation of North and South Stairs.
  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Commence Architectural Precast Installation at the North Elevation.
  • Commence Overhead Plumbing and Electrical Line layout at Lobby Bar.

Office Tower & Studio Theatre

  • Continue Forming and Reinforcing of A3/A4/A5 Office Tower Conference Level.
  • Commence Removal of Reshores at Area B1 & B2 Studio Theater Lobby Level.
  • Commence Formwork for Area A1 Conference Level.

CIP Deck

  • Complete Installation of Area E A1/A2 Level.
  • Complete Forming of Area F1 Elevated Slab A1/A2 Level.
  • Continue Forming and Reinforcing of Area F2 A1/A2 Level.
  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area D Lid Level.

Roadways

  • Continue grading along Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continue Storm Structure Installation along Mt. Vernon Hwy.

Other

  • Continue Georgia Power Trenching at Roswell Road.