Construction Activities for the week of November 3, 2016

Construction Activities This Week

Site/Structure

  • 2016-11-03-1 2016-11-03-2 2016-11-03-3 2016-11-03-4

Performing Arts Center

  • Continued Architectural Precast Installation at the East Elevation.
  • Completed Installation of Ramps at Area C2.
  • Continued SOG Prep of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C1 & C2.
  • Continued Architectural Precast Installation at the North Elevation.
  • Continued Overhead Plumbing and Electrical Line layout at Lobby Bar.

Office Tower & Studio Theatre

  • Completed Removal of Reshores at Area B1 & B2 Studio Theater Lobby Level.
  • Completed Installation of Area A1 & A2 Conference Level.
  • Commenced Forming of A1 & A2 Tenant Level.

CIP Deck

  • Completed Installation of Waterproofing at Area D Lid Level.
  • Completed Installation of Area E1 Lid Level.
  • Continued Fire Protection Installation.
  • Continued Installation of the North Notch.
  • Continued Forming and Reinforcing of Area E2 Lid Level.

Roadways

  • Completed Curb & Gutter Installation at Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Continued Paving Prep at Mt. Vernon Hwy. (Phase 2-Central Portion)

Other

  • Continued Georgia Power Trenching at Roswell Road

Construction Activities Next Week

Site/Structure

  • Continue Slip Ramp Excavation and Shoring Wall Installation.
  • Commence Utility Line Installation to the Performance Art Theatre.
  • Commence Elevator Installation at Precast Deck.

Performing Arts Center

  • Commence Architectural Precast Installation at the West Elevation.
  • Continue SOG prep for North and South Stairs.
  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C1& C2.
  • Continue Architectural Precast Installation at the East Elevation.
  • Continue Overhead Plumbing and Electrical Line layout at Lobby Bar.

Office Tower & Studio Theatre

  • Complete Installation of Area A1 Tenant Level.
  • Continue Forming and Reinforcing of Area A2 Tenant Level.
  • Commence Forming of Area A1 Government Level.

CIP Deck

  • Complete Installation of North Notch.
  • Complete Installation of Area E2 Lid Level.
  • Continue Fire Protection Installation.
  • Commence Installation of Waterproofing at Area E Lid Level.
  • Commence Forming of Area E3 Lid Level.

Roadways

  • Commence paving along Mt. Vernon Hwy. (Phase 2—Central Portion)

Other

  • Continue Georgia Power Trenching at Roswell Road
  • Commence Georgia Power Duct Bank Installation at North Elevation