Construction Activities for the week of November 20, 2015

Current Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Completed H-Pile Installation in West Deck with Kelly Bar: Grid Lines P6-P7 & PH-PM
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and T4 -T6.
  • Began Deep Foundation Installation at Office Building: Grid Line PQ-PS & R6-R8.
  • Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PH & P1-P6.
  • Continued Shotcrete Prep in Southwest Private Deck, West Deck, and East Deck : Grid Line P7—P11 & PA.1-PE.7, PE-PS & P1-P6, and T7-08 at TE.
  • Continued Tie-Backs at Southwest Private Deck, West Deck and East Deck Shoring Walls: Grid Line P7—P9 at PE.7, PG-PH & P1-P0.1, and T7-08 at TE.

Other

  • Activated Temporary Construction Dewatering System Installation.
  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Continued Pre-Blasting Line Drilling in East Deck: Grid Line PB.B-PF.F & P4-P6

Next Week’s Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation in East Deck with Kelly Bar: Grid Lines P4-P6 & PFF-PJJ
  • Commence Grade Beam Excavation at Performing Arts Center: Grid Line WA-WC & W1-T2
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Grid Line WA—WC and T5 – W2.
  • Continue Deep Foundation Installation at Office Build-ing: Grid Line PQ-PS & R6-R8.
  • Continue Shotcrete at Southwest Private Deck, West Deck, and East Deck: Grid Line P7—P11 & PA.1-PE.7, PH-PS & P1-P6, and T7-08 at TE
  • Continue Shotcrete Prep in Southwest Private Deck, West Deck, and East Deck : Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6, and T7-P2 & TE-PJJ.
  • Continue Tie-Backs at West Deck and East Deck Shor-ing Walls: Grid Line PG-PH & P1-P0.1, and T7-08 at TE.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE