Construction Activities for the week of November 17, 2016

Construction Activities This Week

Site/Structure

  • Completed Utility Line Installation to the Performance Art Theatre.
  • Continued Interior Water-Proofing of the Irrigation Cistern.
  • Continued Slip Ramp Excavation and Shoring Wall Installation.
  • Continued Elevator Installation at Precast Deck.

Performing Arts Center

  • Completed Architectural Precast Installation at the East Elevation.
  • Completed Area C1 Roof Installation.
  • Continued Architectural Precast Installation at the West Elevation.
  • Continued SOG Prep of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room.
  • Commenced Erection of Structural Steel at Area C5.

Office Tower & Studio Theatre

  • Completed Installation of Area A2 Tenant Level.
  • Continued Forming and Reinforcing of Area A1Government Level.
  • Commenced Forming of Area A2 Government Level.
  • Commenced Layout & Top Track in Studio Theatre for Wall Framing.

CIP Deck

  • Completed Installation of Area E3 Lid Level.
  • Continued Fire Protection Installation.
  • Continued Forming and Reinforcing of Area F3 Lid Level.
  • Commenced Installation of Waterproofing at Area E Lid Level.
  • Commenced Forming of Area F1 & F2 Lid Level.

Roadways

  • Completed Paving at Mt. Vernon Hwy.
  • Completed striping at Mt. Vernon Hwy.
  • Completed Signalization Installation at Mt. Vernon Hwy/Sandy Springs Circle.
  • Re-opening Mt. Vernon Hwy to Public this week.

Other

  • Continued Georgia Power Trenching at Roswell Road.

Construction Activities Next Week

Site/Structure

  • Complete Sewer Line Install along Johnson Ferry Rd.
  • Complete Interior Water-Proofing of the Irrigation Cistern.
  • Continue Elevator Installation at Precast Deck.

Performing Arts Center

  • Complete Architectural Precast Installation at the West Elevation.
  • Continue SOG Prep of North and South Stairs.
  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room.
  • Continued Erection of Structural Steel at Area C5.

Office Tower & Studio Theatre

  • Complete Installation of Area A1 Government Level.
  • Continue Removal of Reshores at A1/A2 Lobby Level.
  • Continue Forming and Reinforcing of Area A2 Government Level.
  • Commence Forming of Area A1 Roof Level.
  • Continue Layout & Top Track in Studio Theatre for Wall Framing.

CIP Deck

  • Complete Installation of Area F3 Lid Level.
  • Continue Forming of Area F1 & F2 Lid Level.
  • Continue Fire Protection Installation.
  • Continue Installation of Waterproofing at Area E Lid Level.

Roadways

  • Continue Grading of South Parking.
  • Continue Installation of the Storm Structure at South Parking and Mt. Vernon Hwy.
  • Commence Mobilization of Bluestone/Hilderbrand.

Other

  • Continue Georgia Power Trenching at Roswell Road.
  • Commence Georgia Power Jack & Bore Operation at Roswell Road.