  • Completed Installation of Grease Traps North of Office Tower.
  • Completed Backfill at Area D Lid.
  • Continued Slip Ramp Excavation and Installation of Shoring Wall.
  • Commenced Utility Line Installation to the Performance Arts Theatre.
  • Commenced Elevator Installation at Precast Deck.

Performing Arts Center

  • Continued Architectural Precast Installation at the East Elevation and West Elevation.
  • Continued SOG Prep of North and South Stairs.
  • Continued Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room.
  • Commence Steel Erection at Area C5.

Office Tower & Studio Theatre

  • Completed Installation of Area A1 Tenant Level.
  • Continued Forming and Reinforcing of Area A2 Tenant Level.
  • Commenced Forming of Area A1 Government Level.

CIP Deck

  • Completed Installation of Area E2 Lid Level.
  • Continued Fire Protection Installation.
  • Commenced Installation of Waterproofing at Area D4 Lid Level.
  • Commenced Forming & Reinforcing of Area E3 Lid Level.
  • Commenced Forming of Area F3 Lid Level.

Roadways

  • Completed Removal of Southern Utility Pole.
  • Commenced Paving Prep at Mt. Vernon Hwy. (Phase 2—Central Portion)

Other

  • Continued Georgia Power Trenching at Roswell Road.

Construction Activities Next Week

Site/Structure

  • Continue Slip Ramp Excavation and Shoring Wall Installation.
  • Continue Utility Line Installation to the Performance Arts Theatre.
  • Continue Elevator Installation at Precast Deck.

Performing Arts Center

  • Complete Architectural Precast Installation at the East Elevation.
  • Complete Area C1 Roof Installation.
  • Continue Architectural Precast Installation at the West Elevation.
  • Continue SOG Prep of North and South Stairs.
  • Continue Installation of Catwalks and Grating for the Main Trusses at Area C2.
  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room.

Office Tower & Studio Theatre

  • Complete Installation of Area A2 Tenant Level.
  • Continue Forming and Reinforcing of Area A1 Government Level.
  • Commence Forming of Area A2 Government Level.

CIP Deck

  • Complete Installation of Area E3 Lid Level.
  • Continue Fire Protection Installation.
  • Commence Installation of Waterproofing at Area E Lid Level.
  • Commence Forming and Reinforcing of Area F3 Lid Level.

Roadways

  • Commence striping at Mt. Vernon Hwy. (Phase 2—Central Portion)
  • Commence Signalization Installation at Mt. Vernon Hwy/Sandy Springs Circle.

Other

  • Continue Georgia Power Trenching at Roswell Road.
  • Commence Georgia Power Jack & Bore Operation at Roswell Road.