Construction Activities for the week of May 19, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Commenced Raker Beam Form Work Installation.
  • Continued Elevator CE-01 3rd lift Wall Installation.
  • Completed Area C4 Column Formwork & Re-Steel Installation.
  • Continued Area B1 Studio Theatre Foundations & Columns

Building

  • Continued Re-Steel & Installation of O8 Line Structural Wall.
  • Continued Installation of Continuous Footings at Office Tower.
  • Continued Slab on Grade Prep.

Parking Deck

  • Stressed Area H3Tendons.
  • Continued Slab-On-Grade Prep/Excavation in Cast-In-Place Deck.
  • Completed Area G1 Lid Level Formwork & Re-Steel installation and pour at Cast-In- Place deck.
  • Commenced Area G2 Lid Formwork.
  • Completed Mid-level Column installation in Area G2.
  • Completed Precast Parking Deck Slag On Grade Pour.

Roadways

  • Continue Demo and Grading of Mt.Vernon and Sandy Springs Intersection.
  • Continue Installation of Storm line piping.
  • Continue Installation of Bluestone Rd.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Continued Precast Deck – Topping Slab Installation.

Next Week’s Construction Activities

Site/Structure

  • Continue Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Continue Raker Beam Re-Steel Installation.
  • Complete Elevator CE-01 3rd lift Wall Installation.
  • Continue Area B1 Studio Theatre Foundations & Columns.
  • Commence Re-steel installation on South Lobby level Slab.

Building

  • Continue Re-Steel & Installation of O8 Line Structural Wall.
  • Continue Installation of Continuous Footings at Office Tower.
  • Commence Slab on Grade Prep.

Parking Deck

  • Stress Area G1Tendons.
  • Continue Slab-On-Grade Prep/Excavation In Cast-In-Place Deck
  • Complete Area G2 Lid Level Formwork & Re-Steel installation and pour at Cast-In-Place deck.
  • Commence Area G3 Lid Formwork.
  • Complete Mid-level Column installation in Area G3.
  • Continue Area F Footer Installation.

Roadways

  • Continue Demo and Grading of Mt.Vernon and Sandy Springs Intersection.
  • Continue Installation of Storm line piping.
  • Continue Installation of Bluestone Rd.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE.
  • Continue Precast Deck – Topping Slab Installation