Construction Activities for the week of May 12, 2016

This Week’s Construction Activities

Site/Structure

  • Began Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Commence Raker Beam Form Work Installation.
  • Continued Elevator CE-01 2nd lift Wall Installation.
  • Continued Area C4 Column Formwork & Re-Steel Installation.
  • Commenced Area B1 Studio Theatre Foundations & Columns.

Building

  • Commenced Re-Steel Installation of O8 Line Structural Wall.
  • Continued Installation of Continuous Footings at Office Tower.
  • Completed Excavation of Below Grade Elevator Pits.

Parking Deck

  • Stress Area H2Tendons.
  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck.
  • Completed Area H3 Lid Level Formwork & Re-Steel installation and pour at Cast-In-Place deck.
  • Commenced Area G1 Lid Formwork.
  • Completed Mid-level Column installation in Area G1.
  • Continued Area F Footer Installation.

Roadways

  • Continued Demo and Grading of Mt.Vernon and Sandy Springs Intersection.
  • Continued Installation of Storm line piping.
  • Continued Installation of Bluestone Rd.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Continue Precast Deck – Topping Slab Intersection.

Next Week’s Construction Activities

Site/Structure

  • Began Underground Storm Line at Market Square Installation.

Performing Arts Center

  • Commence Raker Beam Re-Steel Installation.
  • Continue Elevator CE-01 3rd life Wall Installation.
  • Complete Area C4 Column Formwork & Re-Steel Installation.
  • Continue Area B1 Studio Theater Foundations & Columns.

Building

  • Continue Re-Steel & Installation of O8 Line Structural Wall.
  • Complete Installation of Continuous Footings at Office Tower.
  • Commence Slab on Grade Preparation.

Parking Deck

  • Stress Area H3Tendons.
  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place deck.
  • Complete Area G1 Lid Level Framework & Re-Steel installation and pour at Cast-In-Place deck.
  • Commence Area G2 Lid Framework.
  • Complete Mid-Level Column Installation at Area G2.
  • Continue Area F Footer installation.

Roadways

  • Continue Demo and Grading of Mt. Vernon and Sandy Springs intersection.
  • Continue Installation of Storm line piping.
  • Continue Precast Deck – Topping Slap Installation.

Other

  • Continue Georgia Power Trenching at Mt. Vernon HWY NE.
  • Continue Precast Deck – Topping Slab Installation.