Construction Activities for the week of May 05, 2016

This Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck

Performing Arts Center

  • Completed Area C3 Column Formwork & Re-Steel Installation
  • Continued Elevator CE-01 Wall Installation Second Lift

Form and Pour North Lobby Balcony

  • Commenced Area C4 Column Formwork & Re-Steel Installation
  • Commence Area B1 Studio Theatre Continuous Footing Prep

Building

  • Completed Excavation & Backfill of O8 Line
  • Continue Installation of Continuous Footings at Office Tower
  • Completed Excavation of Below Grade Elevator Pits

Parking Deck

  • Stressed Area H1Tendons.
  • Completed Area H2 Lid Level Formwork & Re-Steel installation and pour at Cast-In-Place deck
  • Commenced Area H3 Lid Formwork
  • Completed Mid-level Column installation in Area H3
  • Continued Area F Footer Installation

Roadways

  • Continued Demo and Grading of Mt.Vernon and Sandy Springs Intersection
  • Continued Installation of Storm line piping
  • Continued Installation of Bluestone Rd

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Commence Precast Deck – Topping Slab Installation

 

Next Week’s Construction Activities

Site/Structure

  • Continue Slab-On-Grade Prep/Excavation through Middle Point of Cast-In-Place Deck

Performing Arts Center

  • Commence Raker Beam Form Work Installation
  • Complete Elevator CE-01 2nd lift Wall Installation
  • Complete Area C4 Column Formwork & Re-Steel Installation
  • Commence Area B1 Studio Theatre Slab on Grade Resteel installation

Building

  • Commence Re-Steel Installation of O8 Line Structural Wall
  • Continue Installation of Continuous Footings at Office Tower
  • Complete Excavation of Below Grade Elevator Pits

Parking Deck

  • Stress Area H2Tendons
  • Complete Area H3 Lid Level Formwork & Re-Steel installation and pour at Cast-In-Place deck
  • Commence Area G1 Lid Formwork
  • Complete Mid-level Column installation in Area G1
  • Continue Area F Footer Installation

Roadways

  • Continue Demo and Grading of Mt.Vernon and Sandy Springs Intersection
  • Continue Installation of Storm line piping
  • Continue Installation of Bluestone Rd

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Complete Precast Deck – Topping Slab Installation