Construction Activities for the week of March 9, 2017

Construction Activities This Week

Site/Structure

  • Completed Final Slab Pour of the PAC Fountain.
  • Continued Forming of Planters, Site Walls & Stair at the City Green.
  • Continued MEP Installation for the Plaza & Waterwall- Fountain.

Performing Arts Center

  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continued Installation of Brick at North Elevation.
  • Continued Roofing Installation.
  • Continued Installation of Exterior Glass/Glazing at North & East Elevation.
  • Continued Elevator CE-01 Hoist way Prep.
  • Continued Landing Prep of North and South Stairs.
  • Continued Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continued Fire Protection Installation at the Lower Lobby Level, Box Seating and Lobby Bar.

Office Tower & Studio Theatre

  • Continued MEP Overhead Rough-In at Lobby Level.
  • Continued Framing at Gallery Level.
  • Continued CMU Wall Installation at Service Level.
  • Continued Chiller Plant Piping Installation.
  • Continued Roof Level Misc. Steel Install.
  • Continued MEP Overhead Installation at Tenant Level.
  • Continued Installation of Glass/Glazing.
  • Continued High Roof Parapet Framing.
  • Continued Cooling Towers Piping Installation.
  • Continued Architectural Precast Installation at Office Tower.
  • Continued Elevator Installation at Studio Theatre.
  • Continued Roofing Installation at Office Tower.
  • Continued Drywall Installation at Studio Theatre.

CIP Deck

  • Continued Pouring of Curbs.
  • Continued Installation of Waterproofing at Area F Lid Level.
  • Continued Fire Protection Installation.
  • Continued Equipment Room Buildout.
  • Continued Backfill at Area F.

Roadways/Public Utility

  • Continued Grading of South Parking.
  • Continued Sandy Springs Circle East Stormwork.

Construction Activities Next Week

Site/Structure

  • Continued Wall Prep for the PAC Fountain.
  • Continued MEP Installation for the Plaza Fountain.
  • Continue Forming of Planters, Site Walls & Stair at the City Green.

Performing Arts Center

  • Continue Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continue Installation of Exterior Glass/Glazing at North & East Elevation.
  • Continue Installation of Brick at North Elevation.
  • Continue Roofing Installation.
  • Continue Elevator CE-01 Hoistway Prep.
  • Continue Fire Protection Installation at the Lower Lobby Level, Box Seating and Lobby Bar.

Office Tower & Studio Theatre

  • Continue MEP Overhead Rough-In at Conference & Gallery Level.
  • Continue CMU Wall Installation at Service Level.
  • Continue Chiller Plant Piping Installation.
  • Continue Roof Level Misc. Steel Install.
  • Continue Top Track Installation at Conference Level.
  • Continue Installation of Glass/Glazing.
  • Continue High Roof Parapet Framing.
  • Continue Elevator Installation at Studio Theatre.
  • Continue Cooling Tower Piping Installation.
  • Continue Framing at Gallery Level.
  • Continued Architectural Precast Installation at Office Tower.
  • Continued Roofing Installation at Office Tower.
  • Continue Drywall Installation at Studio Theatre.

CIP Deck

  • Commence Striping of the CIP Deck.
  • Continue Pouring of Curbs.
  • Continue Installation of Waterproofing at Area F Lid Level.
  • Continue Fire Protection Installation.
  • Continue Equipment Room Buildout.
  • Continue Backfill at Area F.

Roadways/Utilities

  • Complete Sandy Springs Circle East Roadwork.
  • Continue Grading of South Parking.
  • Commence JF Stormwork.