Construction Activities for the Week of March 4, 2016

This Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Continued PAC Seating Area Slab on Grade Prep.
  • Continued Slab on Grade Installation at Stage Front.
  • Continued Gravel Back Fill & Installation of Water-proofing Along WA Line.
  • Completed Foundation Installation in Area C2: Grid Lines WC-TE.5

Building

  • Continued Deep Foundation Installation at Office.
  • Continued Excavation of O8 Line.

Parking Deck

  • Continued Column Installation at Southwest Cast-In-Place Deck: Gridline PA-PG Line All Footings.
  • Continued Additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Continued (2nd Lift) Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Continued Erection of Precast Panels for Southwest Private Deck.
  • Commenced Slab on Grade Prep in Southwest Private Deck: Gridlines P7-P8.
  • Commenced Slab of Grade Prep: Grid Lines PA-PF.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Dirt Stockpile in at NW Corner of Site Completed.
  • Demobilized One Drill Rig.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Complete PAC Seating Area SOG Pour.
  • Commence Foundation Installation in East PAC – C5 Area. Gridlines: TE.5-ZB.
  • Continue Gravel Back Fill & Installation of Waterproofing Along WA Line.
  • Complete Installation of B1/B2 Cast-In-Place Walls.

Building

  • Continue Deep Foundation Installation at Office.
  • Continue Excavation of O8 Line
  • Commence Footing prep and pour in Area B1.

Parking Deck

  • Continue Column Installation at Southwest Cast-In-Place Deck: Gridline PA-PG Line All Footings.
  • Continue additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Complete (2nd Lift) Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Continue Erection of Precast Panels for Southwest Private Deck: Gridlines PD-PF.
  • Commence Slab on Grade Installation in Southwest Private Deck: Gridlines P7-P8.
  • Commence Slab of Grade Pour: Grid Lines PA-PF.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE