Construction Activities This Week
Site/Structure
- Continued PAC Fountain Slab Walls and Slabs.
- Continued Installation of Storm Drainage above CIP Parking Deck.
- Continued Forming of Planters, Site Walls & Stair at the City Green.
- Continued MEP Installation for the Plaza Fountain.
Performing Arts Center
- Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
- Continued Installation of Brick at North Elevation.
- Continued Roofing Installation.
- Continued Installation of Exterior Glass/Glazing at North & East Elevation.
- Continued Elevator CE-01 Hoist way Prep.
- Continued Landing Prep of North and South Stairs.
- Continued Erection of Steel at Follow-Spot/PAC Lobby Roof.
- Continued Fire Protection Installation at the Lower Lobby Level, Box Seating and Lobby Bar.
Office Tower & Studio Theatre
- Continued MEP Overhead Rough-In at Lobby Level.
- Continued Framing at Gallery Level.
- Continued CMU Wall Installation at Service Level.
- Continued Chiller Plant Piping Installation.
- Continued Roof Level Misc. Steel Install.
- Continued MEP Overhead Installation at Gallery Level.
- Continued Installation of Glass/Glazing.
- Continued High Roof Parapet Framing.
- Continued setting of Cooling Towers & Begin Piping Installation.
- Continued Elevator Installation at Studio Theatre.
- Continued Installation of Planters at the Roof Terrace.
- Continued Drywall Installation at Studio Theatre.
CIP Deck
- Continued Pouring of Curbs.
- Continued Installation of Waterproofing at Area F Lid Level.
- Continued Fire Protection Installation.
- Continued Equipment Room Buildout.
- Continued Backfill at Area F.
Roadways/Public Utility
- Continued Grading of South Parking.
- Continued Sandy Springs Circle East Stormwork.
Construction Activities Next Week
Site/Structure
- Continued Upper Basin Prep for the PAC Fountain.
- Continued MEP Installation for the Plaza Fountain.
- Continue Forming of Planters, Site Walls & Stair at the City Green.
- Continue Installation of Storm Drainage above CIP Parking Deck.
Performing Arts Center
- Continue Landing Prep of North and South Stairs.
- Continue Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
- Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.
- Continue Installation of Exterior Glass/Glazing at North & East Elevation.
- Continue Installation of Brick at North Elevation.
- Continue Roofing Installation.
- Continue Elevator CE-01 Hoistway Prep.
- Continue Fire Protection Installation at the Lower Lobby Level, Box Seating and Lobby Bar.
Office Tower & Studio Theatre
- Continue MEP Overhead Rough-In at Conference & Gallery Level.
- Continue CMU Wall Installation at Service Level.
- Continue Chiller Plant Piping Installation.
- Continue Roof Level Misc. Steel Install.
- Continue Top Track Installation at Conference Level.
- Continue Installation of Glass/Glazing.
- Continue High Roof Parapet Framing.
- Continue Elevator Installation at Studio Theatre.
- Continue Cooling Tower Piping Installation.
- Continue Framing at Gallery Level.
- Continued Installation of Planters at the Roof Terrace.
- Continue Drywall Installation at Studio Theatre.
CIP Deck
- Continue Pouring of Curbs.
- Continue Installation of Waterproofing at Area F Lid Level.
- Continue Fire Protection Installation.
- Continue Equipment Room Buildout.
- Continue Backfill at Area F.
Roadways/Utilities
- Continue Sandy Springs Circle East Roadwork.
- Continue Grading of South Parking.