Construction Activities for the week of March 16, 2017

Construction Activities This Week

Site/Park

  • Continued Forming of Planters, Site Walls & Stair at the City Green.
  • Continued MEP Installation for the Plaza, Interactive & Waterwall Fountain.
  • Commence Final Tie-in of E-10 Storm Structure.

Performing Arts Center

  • Continued Overhead MEP Rough-in at PAC Lower Mechanical Room, Trap & Lobby Level.
  • Continued Installation of Brick at North Elevation.
  • Continued Roofing Installation.
  • Continued Installation of Exterior Glass/Glazing at North & East Elevation.
  • Continued Elevator CE-01 Hoist way Prep.
  • Continued Landing Prep of North and South Stairs.
  • Continued Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continued Fire Protection Installation at the Lower Lobby Level, Box Seating and Lobby Bar.

Office Tower & Studio Theatre

  • Continued Framing at Tenant Level.
  • Continued CMU Wall Installation at Service Level.
  • Continued Chiller Plant Piping Installation.
  • Continued MEP Overhead Installation at Govt. Level.
  • Continued Installation of Glass/Glazing.
  • Continued Cooling Towers Piping Installation.
  • Continued Elevator Installation at Studio Theatre.
  • Continued Roofing Installation at Office Tower.
  • Continued Drywall Installation at Studio Theatre.
  • Commenced Walk-In Cooler Install.

CIP Deck

  • Continued Pouring of Curbs.
  • Continued Fire Protection Installation.
  • Continued Equipment Room Buildout.
  • Continued Backfill at Area F.

Roadways/Public Utility

  • Continued Sandy Springs Circle East Stormwork.
  • Continue JF Stormwork.

Construction Activities Next Week

Site/Park

  • Continued MEP Installation for the Plaza Fountain.
  • Continue Forming of Planters, Site Walls & Stair at the City Green.
  • Continue Final Tie-in of E-10 Storm Structure.

Performing Arts Center

  • Continue Overhead MEP Rough-in at PAC Lower Me-chanical Room, Trap & Lobby Level.
  • Continue Erection of Steel at Follow-Spot/PAC Lobby Roof.
  • Continue Installation of Exterior Glass/Glazing at North & East Elevation.
  • Continue Installation of Brick at North Elevation.
  • Continue Roofing Installation.
  • Continue Fire Protection Installation at the Lower Lobby Level, Box Seating and Lobby Bar.
  • Commence PAC Elevator Install.

Office Tower & Studio Theatre

  • Continue MEP Overhead Rough-In at Government Level.
  • Continue CMU Wall Installation at Service Level.
  • Continue Chiller Plant Piping Installation.
  • Continue Installation of Glass/Glazing.
  • Continue Elevator Installation at Studio Theatre.
  • Continue Cooling Tower Piping Installation.
  • Continue Framing at Tenant Level.
  • Continued Roofing Installation at Office Tower.
  • Continue Drywall Installation at Studio Theatre.
  • Continue Walk In Cooler Install.

CIP Deck

  • Continue Pouring of Curbs.
  • Continue Fire Protection Installation.
  • Continue Backfill at Area F.

Roadways/Utilities

  • Complete Sandy Springs Circle East Roadwork.
  • Continue Grading of South Parking.
  • Continue JF Stormwork.