Construction Activities for the week of June 30, 2016

This Week’s Construction Activities

Site/Structure

  • Commenced Underground Storm Line installation South of Area G.
  • Commenced Underground Duct Bank installation South of Area G.

Performing Arts Center

  • Continued Gallery Level Raker, Formwork and Resteel Installation.
  • Continued Re-Steel Installation at Gallery Level Balcony Wall at Area C5.
  • Poured 2nd lift of WA wall.
  • Poured Gallery Level Slab at Area C6.
  • Completed CIP Footing and Column Installation at Studio Theatre.

Office Tower

  • Continued Installation of Continuous Footings at Office Tower at Area A.
  • Continued Installation of Elevators AE01 & AE02 Elevator Pit.
  • Completed Re-Steel & Installation of Foundation.
  • Structural Wall Adjacent to 08 Line Wall.

Parking Deck

  • Commenced footing installation at Area E.
  • Continued Column/Shear Wall Installation at Area F.
  • Continued Waterproofing on Lid.
  • Continued pouring of footings at Area D.
  • Completed backfill of the lid at Area H.
  • Completed footing installation at Area F.

Roadways

  • Continued Grading along Mt. Vernon.
  • Continued Installation of Bluestone Rd.
  • Continued Fidelity Bank Retaining Wall Installation.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Continued Precast Deck – Topping Slab Installation.

Next Week’s Construction Activities

Site/Structure

  • Complete Underground Storm Line Installation South of Area G.
  • Complete Underground Duct Bank installation South of Area G.

Performing Arts Center

  • Continue Re-Steel installation 3rd lift on WA Wall—West Stage.
  • Continue Gallery Level Raker, Formwork and Resteel Installation.
  • Commence Slab on Grade in Studio Theatre.

Office Tower

  • Continue Installation of Continuous Footings at Office Tower.
  • Completed Installation of Elevators AE01 & AE02 Elevator Pit.

Parking Deck

  • Continue Column/Shear Wall Installation at Area F.
  • Continue Slab on Grade Prep at Area F.
  • Continue Waterproofing on Lid.
  • Continue Area D & E Footing Installation.

Roadways

  • Continue Underground Utility work on Mt. Vernon working East.
  • Continue Grading along Mt. Vernon—Continuing East.
  • Continue Installation of Bluestone Rd.
  • Complete Fidelity Bank Retaining Wall Installation.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE.
  • Complete Precast Deck – Topping Slab and Barrier Cable Installation.