Construction Activities for the week of June 23, 2016

This Week’s Construction Activities

Site/Structure

  • Continued perimeter drain installation of the lid.

Performing Arts Center

  • Continued Re-Steel Installation at Gallery Level Balcony Wall at Area C5.
  • Poured 1107 Gallery Level Elevated Slab.
  • Poured Lobby Level North Restroom Slab.
  • Poured Formwork & Re-Steel Installation of North Balcony Wall 3rd lift.
  • Poured North Balcony Gallery Level Elevated Slab.
  • Continued CIP Footing, Column, & Wall Installation at Studio Theatre.

Office Tower

  • Continued Re-Steel & Installation of Foundation Structural Wall Adjacent to 08 Line Wall.
  • Continued Installation of Continuous Footings at Office Tower.
  • Continued Installation of Elevators AE01 & AE02 Elevator Pit.

Parking Deck

  • Commenced backfill of the lid at Area H.
  • Continued Footing & Column Installation in Area F
  • Continued Waterproofing on Lid.
  • Commenced excavation of footings at Area D.

Roadways

  • Continued Grading along Mt. Vernon.
  • Continued Installation of Bluestone Rd.
  • Continued Fidelity Bank Retaining Wall Granite Veneer Installation.
  • Completed demolition of house along Hilderband Drive.

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE.
  • Continued Precast Deck – Topping Slab Installation.

Next Week’s Construction Activities

Site/Structure

  • Continue Underground Storm Line at Market Square Installation.
  • Commence Underground Storm Line installation South of Area G.

Performing Arts Center

  • Continue Re-Steel installation 3rd lift on WA Wall—West Stage.
  • Pour Gallery Level Slab at Area C6.
  • Commence Gallery Level Raker, Formwork and Resteel Installation.
  • Complete CIP Footing, Column, & Wall Installation at Studio Theatre.
  • Commence Slab on Grade Prep in the Studio Theatre.

Office Tower

  • Complete Re-Steel & Installation of Foundation Structural Wall Adjacent to 08 Line Wall.
  • Continue Installation of Continuous Footings at Office Tower.
  • Complete Installation of Elevators AE01 & AE02 Elevator Pit.

Parking Deck

  • Continue Footing & Column Installation in Area F.
  • Commence Slab on Grade Prep – Area F.
  • Continue Waterproofing on Lid.

Roadways

  • Continue Underground Utility work on Mt. Vernon working East.
  • Continue Grading along Mt. Vernon—Continuing East.
  • Continue Installation of Bluestone Rd.
  • Complete Fidelity Bank Retaining Wall Installation.

Other

  • Continue Georgia Power Trenching at Mount Vernon NWY NE.
  • Complete Precast Deck – Topping Slab Installation.